INTERNATIONAL JOURNAL OF LATEST TECHNOLOGY IN ENGINEERING,
MANAGEMENT & APPLIED SCIENCE (IJLTEMAS)
ISSN 2278-2540 | DOI: 10.51583/IJLTEMAS | Volume XIV, Issue III, March 2025
www.ijltemas.in Page 370
An Assessment of Public Procurement Process of Enron Nigeria
Power Holdings Electrification Project
Olabode Segun Oluwaseun Phd., Daniel Deborah Damilola
Department of Project Management Technology, Lagos State University
DOI : https://doi.org/10.51583/IJLTEMAS.2025.140300040
Received: 29 March 2025; Accepted: 02 April 2025; Published: 17 April 2025
Abstract: Though, public procurement process is one of the main strategic pillars of good governance and service delivery, it is
also one of the most vulnerable activities of government as the number of litigations against Nigeria both locally and
internationally of which Enron and Enron Nigeria Power Holdings are typical example. Earlier assessment of Enron
electrification activities around the world shows that most of researches and stakeholders focused on the legal aspect and
implication, corporate governance, and on audit and finacial fruad. This study examined the causes of the project failure from the
procurment angle. This study adopted qualitative analytical technique, using an exploratory research design. Secondary data were
extracted from case file in courts, researches and articles on stakeholders’ website. This study deduced among others that, Single
Source or Sole Sourcing was used without following the condition required for its used. It also observed that, none of the
procurement process was considered before the power purchase agreement was signed. The study thus recommended among
others that, core principles of sole sourcing should be use if it should be adopted or adapted in any procurement process to
improve the negotiating power of the project owner and the review of the 2007 procurement act by procurement expert to address
the lapses that could cause further litigations
Keywords: Public Procurement Process, Enron, Electrification Project, Sole Sourcing, Procurement Act
I. Background to the Study
The rapid rate of transformation the world economy is experiencing is unprecedented. This can be exemplified with noticeable
breakthroughs in Renewable Energy Growth-solar and wind electrification (Olabode, 2018). Olabode further noted that, a
nation’s electricity capability has been proven in history of having an enormous influence on the economic growth.
However, Nigeria has experienced more epileptic supply of electricity for major part of her existence despite been the fifth
country in the world after USA, UK, Germany and Italy to installed electric generators in 1896 (Nnamani, 2023; Olabode, 2018).
Though, Momodu (2010) believed Nigeria is the third nation after USA and the UK.
Series of policies at different levels of government had been implemented to improve the electric power supply with none given a
desirable solution. At federal level, the notable differs reformation begin in 1896 with the Public Works Department (PWD). This
was changed to the Nigeria Electricity Supply Company (NESCO) in 1929 and then to Electricity Cooperation of Nigeria (ECN)
in 1951 and the Niger Dam Authority (NDA) in 1962. Then the merger of ECN and NDA to form the Nigerian Electric Power
Authority (NEPA) whose nomenclature later changed to Power Holding Company of Nigeria (PHCN) in 2005 (Edomah, Foulds,
& Jones, 2016; Folorunso & Olowu, 2014; Olabode, 2018). And the present policy implementation of unbundling PHCN into
generation, transmission and distribution companies in 2013, which only resulted in change of nomenclature comparing the
investment to the output gives little or no services improvement.
Few state governments in Nigeria especially Lagos State, also made attempt to engaged the service of Independent Power
Generators. This initiative of the then Bola Ahamed Tinubu led administration in Lagos State raised an initial hope but was short
live by both the collapse of Enron due to bankruptcy and the comment of the World Bank on the procurement process (Olukoju,
2003; Ikem, 2022).
Though, public procurement process is one of the main strategic pillars of good governance and service delivery, it is also one of
the most vulnerable activities of government that is exposed to waste, fraud corrupt practices etc. due to the financial volume
involved (Organisation for Economic Co-operation and Development-OECD, 2021). One major reason for The World Bank
suspension of the initiative was procurement processes. . Based on this, there is a need to carefully examine the processes that are
observable based on available literatures to investigate the Enron project in Nigeria. This will show how public administrators
and other authorised managers could have used public procurement processes to saved Nigeria of the subsequent embarrassment
and financial waste of eleven million dollars that have risen to twenty-two million dollars as at 2020. This was the amount
awarded against the nation by International Criminal Court (ICC) in favour of Enron Nigeria Power Holding, Ltd. (ENPH) for
negligence in the procurement processes (Owolabi, 2020).
Statement of the Problem
According to (Bassey, 2018), Nigeria could have been plagued into the worst recession with the two arbitration awards against
the nation in the sum of $8.9bn (about N2.7 trillion at CBN’s N305.4 as of May 2022). These are in favour of Process &
INTERNATIONAL JOURNAL OF LATEST TECHNOLOGY IN ENGINEERING,
MANAGEMENT & APPLIED SCIENCE (IJLTEMAS)
ISSN 2278-2540 | DOI: 10.51583/IJLTEMAS | Volume XIV, Issue III, March 2025
www.ijltemas.in Page 371
Industrial Development Limited (P&ID) and ENPH. The cause of the litigation is the procurement Nigeria seek from the two
organisation that needs to be revoked due to anomalies observed in the processes of acquisition.
This study focused on the ENPH project because of its peculiarity to the Nigeria political and social environment. Many accusing
fingers had been raised in the media, especially in the political environment in Nigeria on the failure of the Enron project
considering the initial hope it raised among Lagosian (Olawale, 2004). Despite the array of available legal documents-Enron v.
Nigeria and others (2012); Enron Nigeria Power Holding LTD Appellee V. Federal Republic of Nigeria Appellant (2016) etc.
that shows some of the activities that transpired among the parties involved in the project in Nigeria and few researches on failed
Enron projects around the world, researchers, technocrats and other stakeholders have relatively not shed enough light to
identified the abundant knowledge and public managerial lessons from the failed project.
Few researches and stakeholders have either partially or whole examined Nigeria Enron project scandal. But majority of them
have focused on the legal aspect and implication- Clowes (2021); Jus Mundi (2022); Ukpe (2021) etc. or on corporate
governance- Center for Ethical Organizational Cultures (2023); Muraina, Enyinna, & Stella (2010); Okoye & Gbegi (2013) etc.
and on audit and finacial fruad- Audu (2018); Moses (2019); Olusola (2022) etc. However, the scandal have rarelly been
examined from the procurment angle which is part of the main reason the World Bank seeks for the renegotiation of the procured
service and subsequently leads to the cancellation of the project. This study seeks to feel this gap in the body of knowledge by
examining the procurement process in the acquisition of the project.
Objective of the study
The main objective of this study is to compare the model in the acquisition of Enron Nigeria Power Holdings service with the
standard procurement process. However, the specific objectives are to:
i. Examine the procurement process used to acquire ENPH project in 1999.
ii. Investigate the shortcomings of procurement act as compared to the standard procurement principles.
iii. Determine effect of the result of the comparison of the process in ENPH project and the standard procurement processes
impact on National development.
Research Questions
This study attempt to provide answers to the research questions stated below:
i. What was procurement process used to acquire the ENPH project in 1999
ii. What are the shortcomings of the procurement act as compared to the standard procurement principles
iii. How can the result of the comparison of the process in ENPH project and the standard procurement processes impact on
National development.
Significance of the Study
Management: The recommendations of this study could be of immerse value to the decision makers of both public and private
enterprises that are presently experiencing similar decline in efficiency and litigation in their procurement activities. This is
because, the study addressed some of the most critical factors relating to procurement process and expected function of a
procurement officer.
Public Vendors: With the increased number of private participants interested in investing with the Nigerian government
especially in the PPP model, the study is of important to investors to be able to understand the peculiar challenges and
opportunities in Nigeria public procurement activities.
Policy makers: The study findings are of value to the government, stakeholders and other groups or individuals in position of
authority, because, it brings into light the scope, advantage, detriment and limitation of the divers’ procurement policies that
could result on negative outcome or fraud. It thus provides a bases for development or redesigning of an improve procurement
Act for the Nation.
Academicians: This study is of immerse value to scholars and academicians as they can benefit from the conceptual, theoretical
and this study findings on factors that hinder the benefit of standard Procurement Process in Nigeria. In addition, it presents a
bases for researches in the field of procurement and logistics for further research and consultancy.
Scope and Limitations of the Study
Though there are numerous fraudulent procurement that can be identify both in Nigeria and internationally, but this study is
limited to the Enron project because of the controversies it has generated both in Nigeria and internationally. In Nigeria it has
generated a lot of political and legal controversies. While among managers, researches and other stakeholders the focus had
mostly been on corporate governance, fraud and accounting, thus this study will limit its view to the procurement activities that
causes the World Bank to seek for renegotiation of the entire project. Also Project Management institute explained two scenarios
of procurement process, the first is procurement planning, solicitation planning, solicitation, source selection, contract
INTERNATIONAL JOURNAL OF LATEST TECHNOLOGY IN ENGINEERING,
MANAGEMENT & APPLIED SCIENCE (IJLTEMAS)
ISSN 2278-2540 | DOI: 10.51583/IJLTEMAS | Volume XIV, Issue III, March 2025
www.ijltemas.in Page 372
administration, and contract close-out. The second is plan procurement management, conduct procurements,
control/administering procurements and close procurements. This study will focus more on the first scenario because it is more
explanatory and more elaborate.
II. Literature Review
Includes review of existing studies in line with the research study, theoretical review (models and theories underlying the
research study) and empirical review (methodological review of studies pertaining to the topic under study).
Conceptual Review
Procurement
According to Jerkins (2024) process of acquiring goods or services is refers to as procurement, procurement teams’ work together
to obtain competitive price that gives best value. While Jacob (2022) explain it as the act of obtaining all the materials and
services that are required for a project.
Julie (2023) defines Procurement as the method of obtaining or purchasing goods or services for business purposes. Furthermore,
there is need for the authority to identified a need and decided on its procurement requirement. It also covers the ultimate disposal
of property at the end of its useful life (Kalu et al, 2020).
According to The United Nations all methods of acquiring goods, professional works, and services, including all phases of
procurement from needs identification to the end of the project is regarded as procurement (Kelvin et al, 2021)
Procurement includes all functions of purchasing which involves acquiring goods, works and services up till contract award
(Jasline, 2018).
The steps in acquiring property or services, starting with the process for determining a need for property or services and ending
with contract completion and closeout is called procurement (Robert & Clifford, 2004).
Based on the above this study adapted the conceptual view of Robert & Clifford (2004) and thus believed, Procurement includes
all stages of the process in the acquisition of products and/or services from outside the performing organisation or project team,
starting with the process for determining a need and ending with the completion of the desired output with an audited report of
the process as a feed for future procurement process.
Public Procurement
Public funded project by the government is refers to as public procurement (Yusuff, 2023). A lot of reforms has been
implemented by the government because of the huge amount of public funds involve for the main purpose of ascertaining
efficiency and value for money (Odhiambo & Kamau, 2023). Government has adopted a more advance system which requires the
use of electronic procurement system, development of procurement act and regular monitoring (Masoud et al., 2021: Torvatn &
de Boer, 2017).
All goods and services procure for both the federal and states use with public fund is regarded as public procurement (Kelvin et
al, 2021).
All process of procuring goods, services, works, state enterprises by the state is defined as Public procurement which must be in
accordance with the principle of public procurement is refers to as public procurement (Saeed & Chunlin, 2019).
The reason for public procurement and the development of public procurement Act 2007 was to make public procurement
processes more professional, efficient, and effective (Mohammed et al. , 2022)
From the above this study adapted the conceptual view of Kelvin et al (2021) and thus believed, Public procurement is
purchasing of goods and services for federal, states and local using public funds. This process is guided by roles and regulations
which is to be in line with international standards.
Procurement Process
Marijn (2024) defines procurement process as the set of steps in acquiring goods and services and ensure cost optimization.
The process of identifying goods and services, sourcing of suppliers that meets the business objectives, negotiation of cost,
purchases and delivery of the items are steps in procurement process. The researchers identify nine core steps, but further states
that they are various procurement processes depending on each company’s structure and needs, the nine core steps are
Identification of company needs, Submission of purchase request, Assessing and selection of vendors, Negotiate price and terms,
Creation of a purchase order, Receive and inspect the delivered goods, Conduct three-way matching, approve the invoice and
arrange payment and Keeping of records (Jenkins, 2024).
Stages involves in procurement process starts with needs identification, evaluation and Selection, Negotiation of contract,
Purchase Order Processing, Delivery and Inspection, Performance Assessment and Relationship Management, Invoice Processing
and Payment, Reconciliation and Record Keeping (Karan, 2024).
INTERNATIONAL JOURNAL OF LATEST TECHNOLOGY IN ENGINEERING,
MANAGEMENT & APPLIED SCIENCE (IJLTEMAS)
ISSN 2278-2540 | DOI: 10.51583/IJLTEMAS | Volume XIV, Issue III, March 2025
www.ijltemas.in Page 373
There are series of steps used by an organization in order to obtain goods or services for their goals and objectives. The steps are
as follows: identify goods or services needed, evaluate and select a supplier, negotiate the terms of the trading agreement with
selected supplier, finalize the purchase order, receive invoice and process payment, delivery and audit of the order, maintain
accurate record of invoices (Elizabeth, 2023)
This study observed from PMBOK (2017); Project Management Institute (2013) etc. procurement processes/steps/phrases may be
divided into as many as possible, he further provides an overview of two researcher. The first researcher identifies the
processes/steps/phrases of procurement to be six (6) and they are procurement planning, solicitation planning, solicitation, source
selection, contract administration, and contract close-out. The second researcher identifies procurement processes as four (4) plan
procurement management, conduct procurements, control procurements and close procurements.
The most widely used model for procurement process in project management are seen in figure 1 and 2. This study adapted Karan
concept with the stages ranging from the inception of needs identification up till the last stage when reconciliation is done and
record as data base for future use.
Figure 1: Procurement process
Source: Introduction to Project Procurement and Contract Management (Project Management Institute 2013 and PMBOK 2017)
OR
Figure 2: Procurement process
Source: Introduction to Project Procurement and Contract Management (Project Management Institute 2013 and PMBOK 2017)
INTERNATIONAL JOURNAL OF LATEST TECHNOLOGY IN ENGINEERING,
MANAGEMENT & APPLIED SCIENCE (IJLTEMAS)
ISSN 2278-2540 | DOI: 10.51583/IJLTEMAS | Volume XIV, Issue III, March 2025
www.ijltemas.in Page 374
Brief History of Enron Corporation
The merger of Houston Natural Gas of Houston, Texas and InterNorth, Omaha, two of the major gas pipeline companies in USA
in 1985 led to the creation of Enron Corporation with an initial name InterNorth-Houston Natural Gas (Watkins, 2006). The
name Enron was adopted in 1986 (Bondarenko, 2024). Watkins (2006) also noted that, the headquarters was first at Omaha, it
was later moved to Houston due business reasons. Houston is seen as the center of the energy industry for natural gas firms. This
movement occurred after the first head of the merger Sam Segnar was replaced with Kenneth Lay.
The organisation is a vendor in natural gas, electricity (as a generator, transmitter and distributor of electricity), communications
and market & transports of natural gas to consumers in the United States and do other commodities servicing globally (Center for
Ethical Organizational Cultures, 2023). Enron involvement in electricity is vast, as it develops, constructs and operates power
plants, pipelines, and other energy-related projects globally.
In the1990s, Ken Lay-chairman, Jeffrey Skilling-Chief Executive Officer, and Andrew Fastow- Chief Financial Officer
reorganised the organisation into a $150 billion energy entity recognised by Wall Street as an investor in energy contracts and
markets (Center for Ethical Organizational Cultures, 2023).
Enron become the seventh largest publicly traded corporation in the United States by 2001, and it is regarded as the most
Innovative Company in America for six consecutive years. Enron’s collapse was alleged to be characterised by fraudulent
practices. The collapse resulted in an average 25,000 jobs, $2 billion in pension savings and $1.2 billion retirement funds lost.
Arthur Andersen LLP, Enron’s auditor and one of the largest accounting firms in the world, was so marred by its role in the
scandal (Levin Center, 2021).
Procurement Process used for ENPH project in 1999
Procurement(s) by government and its agencies before the 2007 procurement act was enacted were governed by the Finance
(Control and Management) Act, 1958, together with the Financial Regulations which (Ekpeniho, 2003). However, Adewoyin
(2023) explained the lapses in the procurement which is conducted by financial regulations instead of Statute (a law set by
legislative, act of corporation, or an international instrument setting up an agency and regulating its scope or authority) or process
of acquisition (a guided procurement process which already includes a contract expert for the statute). The financial regulations
were used by finance ministry in the award of a contract, and it was guarded in secrecy. Thus, Shwarka & Natalia (2012) believed
the 1958 model of procurement exposed the nation to significant level of irregularities and delay in project delivery before the re-
emergency of democratic governance in 1999.
To Shwarka & Natalia, this is as a result of lack of fiscal transparency, public accountability, poor project planning, adoption of
inappropriate procurement methods, contract allocation as against competitive tender, poor project documentation, lack of
transparency in the tendering process.
Thus, as at when ENPH signed Memorandum of Understanding (MOU) with Lagos state, there was no public procurement act.
the only act for public procurement was guided by the Finance(Control and Management) Act, 1958, together with the Financial
Regulations, with its objectives clearly focus on financial regulations. However, as observed in figure 1 & 2, financial regulation
is just a subset of procurement process. This can also be observed in the activities among the major stakeholders as state in the
case file in court which all parties did not object to in court as shown in Table 1. The financial regulation is not what was
contested in court but the procurement management lapses that were not considered before the Power Purchase Agreement
(PPA).
Table 1: Activities Among the Major Stakeholders as Stated in the Case File in Court
In 1999, Lagos State, a regional government in Nigeria, was "in desperate need of energy
June 19, 1999
By letter of June 19, 1999, Enron International expressed interest in working with Lagos
State, stating that “Enron is the highest-ranking power and gas company and is the leading
company worldwide in such industry.
July, 1999
Enron formed ENPH as a special-purpose vehicle to construct and operate power plants in
Lagos State
August 13, 1999
A Memorandum of Understanding (MOU) was signed by the Lagos State Government, on
the one hand, and ENRON Power Nigeria Ltd. and Yinka Folawiyo Power Limited (a
Nigerian power company), on the other. The MOU was on the construction of a 560
megawatts gas turbine power plant in two phases at a cost of about $800 million
November 17,
1999
ENPH representatives and an employee of Enron International met with representatives of
Nigeria, including President Obasanjo of Nigeria and the Governor of Lagos State. At the
meeting, ENPH gave a PowerPoint presentation touting Enron’s vast financial and
technical capability and describing Enron as the company with which ENPH was
“affiliated.”
INTERNATIONAL JOURNAL OF LATEST TECHNOLOGY IN ENGINEERING,
MANAGEMENT & APPLIED SCIENCE (IJLTEMAS)
ISSN 2278-2540 | DOI: 10.51583/IJLTEMAS | Volume XIV, Issue III, March 2025
www.ijltemas.in Page 375
December 6,
1999
Nigeria, Lagos State, the National Electric Power Authority of Nigeria (“NEPAN”), and
ENPH executed the (Power Purchase Agreement) PPA, with ENPH as “Owner” of the
energy facilities, Lagos State as “Purchaser” of the energy, NEPAN as regulator of the
facilities it would connect to Nigeria’s power grid, and Nigeria as “Guarantor.”
Note: Enron was not a party to the PPA, nor was its participation in the construction
project mentioned in the PPA.
December 7;
1999
El-Rufai the first Director General, Bureau of Public Enterprises (BPE) examined the project
December 10;
1999
World Bank report on the ENPH project was delivered to the office of the presidency,
Lagos state government and NEPAN to express economic criticisms of a draft of the PPA.
December 10;
1999
El-Rufai Report shows that the PPA agreement was not in line with the electric sector reform
and privatisation and it would have a massive negative effect on NEPA-possibly make the
organisation bankrupt
December 15;
1999
NEPAN wrote to ENPH that implementation of the PPA was "stayed until further notice.
January 2000
Nigeria's President informed Lagos State that, the Attorney General of Nigeria had concluded
the PPA was invalid under Nigerian law and suggested that the PPA be renegotiated.
June 2000
The parties agreed to an amended PPA regarding Phases I and III along with Enron
Nigeria Barge Ltd., to which ENPH had transferred its rights and obligations with respect
to those phases. Thereafter, AES Nigeria Holdings Ltd. (“AES”) acquired the rights to
Phases I and III, along with an option to purchase Phase II, provided agreement was
reached with Nigeria on amending the PPA
December 31,
2000
As regards Phase II, ENPH's obligations were contingent upon satisfaction of certain
conditions by December 31, 2000, including possession of a plant site, all necessary
easements from Lagos State and Nigeria, and a security letter of credit.
November 2001
Enron’s collapse became public knowledge, and it filed for Chapter 11 bankruptcy
protection on December 2, 2001. The same day, ENPH wrote to the Nigerian parties that
ENPH would be unaffected by the bankruptcy and remained free to perform its obligations
under Phase II. Nigeria apparently did not respond. AES contacted ENPH to express
interest in extending its Phase II option; ENPH did not respond and the option expired
Source: Extract from Case 15-7121 Activities on Enron Project in Nigeria as filed in the appeal in 1999
World Bank review on ENPH
The following were World Bank review on ENPH
1. The lack of transparent and competitive bidding, the deal should have been competitively bid
2. That the final contract was overly favorable to Enron.
There is concerns about terms which was viewed to be too favorable for Enron due to the following:
1. The type of fuel to be used. There was no separate fuel supply agreement; instead, fuel was to be provided by NEPA
(subsequently PHCN), which would contract it directly from the Nigerian Gas Company
2. The fact that the plant would not be penalized for poor performance;
3. Excessive contract termination payments payable in U.S. dollars with no deduction of taxes
4. That capacity payments were deemed too high.
Capacity payments were to be US $ 19.91/KW-month, multiplied by the tested capacity of the Power Plant.
Theoretical Framework
Public Interest Theory of Regulation
This was initially established by Arthur Cecil Pigou in 1932, and he stated that in response to public demand, regulation should
be used in correcting any irregularities in the market practices. According to Hawkins (2020) to properly manage resources
regulations guiding the distribution need to be drafted for optimization.
INTERNATIONAL JOURNAL OF LATEST TECHNOLOGY IN ENGINEERING,
MANAGEMENT & APPLIED SCIENCE (IJLTEMAS)
ISSN 2278-2540 | DOI: 10.51583/IJLTEMAS | Volume XIV, Issue III, March 2025
www.ijltemas.in Page 376
Regulations by government plays a major role in process development by eliminating imperfect competition from the market
(Thairu & Chirchir, 2016). Regulation is a tool used by the state in achieving productive distribution of resources (Shubik, 1970).
Procurement policies should be put into action and this may involve implementation methods. It gives room for all a sundry to
compete for contracts without receiving any special consideration during the procurement process (Simayi, 2005).
Public Value Theory
Moore (1995) states that the importance of public value theory is to create something that is of beneficial to the public which is
the primary objective of the government. Williams and Shearer (2011), confirm that the managers working in the public sector
are beneficiary to the theory despite obstructions and heavily tasked in making procurement decisions for improving the lives of
the general public.
The idea is that value is created or generated because of the activities carried out by public institutions and the managers of those
institutions (Benington & Moore, 2011). Quality and services are affected by bidding which is a function performed by
Procurement managers. However, procurement managers and employees are expected to focus on public values and avoid
political influence (Silas & Sammy, 2022).
This study will be based on public interest theory of regulation and public value theory, because in general the priority of the
public sector agencies is to gives room for all a sundry to compete for contracts without receiving any special consideration
during the procurement process as stated by Simayi (2005) and also the public values should be of greatest priority according to
Moore (1995) who stated that the primary objective of the government is to create something that the general populace views as
beneficial to them.
Empirical Review
Sope (2015) research is on a Comparative Analysis of the Nigerian Public Procurement Act against International Best Practice, to
determining whether the Public Procurement Act meets the requirements of international best practice. The study was also carried
out to examine what may be regarded as international best practice in the public procurement context and analyses whether the
Nigerian Public Procurement Act contains provisions which accord with this practice. Factors limiting the adoption of
international best practice in the Nigerian context were analyses. The finding shows that the Nigerian Public Procurement Act has
included some of the requirements of international best practice, but several challenges of procurement process still remain even
when it follows the requirements of Public Procurement Act. The researchers recommended the reassessment of Nigerian
procurement system in capacity building for effective management of procurement process, Procurement officials should also be
protected from interference by politicians. Sope (2015) view looked at the Nigerian Public Procurement Act in line with the core
principles of international practice and not at the processes of procurement which this study tends to address.
Shwarka and Anigbogu (2012) research on impact of the public procurement reform on public building projects delivery in
Nigeria. To analyse the impact of the public procurement reform on public building projects delivery in Nigeria. The finding
shows that there is no significant difference between the mean responses of stakeholders with regards to the reforms impact on
irregularities associated with public building projects delivery in Nigeria. Constraint observed to have impact on public project
delivery were inadequate project/budgeting plans by the client and the project team. The researchers recommended the use of
competent staff in carrying out procurement steps ranging from needs identification, realistic estimates, methods of tendering to
solve the problem of delays in projects execution. Public Procurement Act provision is to sanctioning corrupt practices at all
levels. The study dwell more on implementation of Public Procurement Act and how to prevent project delay due to processes
and the use of incompetent staff but not on process of procurement.
Stuart and John (2011) carried out a research on Corporate Governance Post-Enron: Effective Reforms, or Closing the Stable
Door, to provide insights as to the efficacy of recent governance reforms in Enron collapse. The finding shows that Enron failure
is due to governance. Internal controls and reduction in conflicts of interest could play a major role reduction of fraudulent
behavior. The study viewed Enron’s collapse from governance perspectives but this study looks at Enron project from
procurement process perspective as the major reasons why Nigeria is trapped in debt from ongoing arbitration as seen in different
case studies.
III. Research Methods
This study adopted an exploratory research design. This is because the possibility of getting real fact from people and
stakeholders to make it quantitative is slim, due to the political terrain involved. As there are accusation and counter accusation
from political parties and supporters within the political terrain thereby creating a high possibility of a bias extraction of survey
through questionnaire. The data is thus extracted from case file in courts, researches and articles on stakeholders’ website. This
means the study used an inductive qualitative approach. This enabled the study to investigate and understand the issues and
identify opportunities for additional investigation as noted by Azungah (2018)
Though there are few publications related to the study examined, this study used convenience sampling and thus focused more on
ten (10) publications (books, Article, case file and Information from international body’s website) as reflected in table 2 to draw
its observations. This means secondary data from these publications were used to answer the research questions. Papers were
reviewed in line with the study area and this includes case file in courts, journals, conference proceedings and articles
INTERNATIONAL JOURNAL OF LATEST TECHNOLOGY IN ENGINEERING,
MANAGEMENT & APPLIED SCIENCE (IJLTEMAS)
ISSN 2278-2540 | DOI: 10.51583/IJLTEMAS | Volume XIV, Issue III, March 2025
www.ijltemas.in Page 377
Table 2: Sampled Case File in Courts, Journals, Conference Proceedings and Articles
S/N
Authors
Extracted Information
1
United States Court of
Appeals for the district
of Columbia circuit
Extracted case: Enron Nigeria Power Holding, Ltd.V.Fed. Republic Of Nigeria 844
F.3d 281 (D.C. Cir. 2016) Decided Dec 27, 2016
2
Stuart Gillan & John
D. Martin (2007)
Journal of Corporate Finance 13(5):929-958 DOI:10.2139/ssrn.977585, Corporate
Governance Post-Enron: Effective Reforms, or Closing the Stable Door? (2007)
The study findings revealed that corporate governance failed at Enron the firm's
viability ultimately rested on an inherently risky business strategy, a strategy that the
board and others apparently failed to understand
3
International
commercial arbitration
analyses (2006)
Extracted case : ICC Case No. 14417/EBS/VRO/AGF, Enron Nigeria Power Holding
Ltd v. (1) Lagos State Government (2) Federal Republic of Nigeria (3) Power Holding
Company of Nigeria (2006)
4
Casetext: Smarter
Legal Research (2016)
Enron Nigeria Power Holding, Ltd., Appellee v. Federal Republic of Nigeria,
Appellant (2016). The Court finds that permitting ENPH additional time to effect
service by alternative means will not prejudice Nigeria, which appears to be using this
action to re-litigate and delay the payment of claims already resolved by the agreed
upon arbitration procedure
5
Negotiation experts
(2021)
Extracted case: A Negotiation Case Study: Exploring the Enron Case in India
6
www.forbes.com
Enron's Nigeria Barge: The Real Deal (2004)
7
Project Management
Institute (2013)
Procurement process extraction
8
PMBOK (2017)
Procurement process extraction
9
Rajesh Kumar &
Verner Worm (2011)
Extracted case: Negotiating in India: Some Case Studies
10
World Bank (2020)
Extraction of procurement principles
Source: Field Survey
IV. Discussion of Findings
Though, this study is limited to procurement processes, an observation of the then corporate culture of Nigeria as a system played
a major role on ethical practices that characterised the ENPH project in Nigeria.
Just as observed by Rashid (2020) from his study on the “Collapse of Enron Corporation” the major players had major influence
on the termination of the project contract and the subsequent litigation that followed. This study observed that, the Corporate
Culture or what Khan & Panarina (2017); Ilona & Ērika (2007) etc. referred to as National Culture (when it concerned national
issues) and leadership played a major role in the unethical practices that characterised procurement of the ENPH project.
Enron financial instability and fraudulent practices was covered up by their reputable accounting firm “Arthur Anderson”-Rashid
(2020)-as at the time of signifying their intention to generate electricity for Lagos state took advantage of the vulnerable national
or corporate culture of the system. The study observation on the vulnerability of the Nigeria national culture was based on three
facts.
Firstly, Lagos state does not have the constitutional right according to the 1999 constitution to generate, transmit and distribute
electricity since the area the ENPH project was to cover has been covered by the national grid (Sipasi & Ofagbor, 2023).
Memorandum of Understanding (MoU) was signed with ENPH as the owner of the project before notifying the federal
government.
Secondly, the Finance (Control and Management) Act, 1958, together with the Financial Regulations used by both the state and
the federal government as at 1999 for procurement and did not make provision for single source procurement process that can
enable Lagos state government to choose ENPH alone as the only organisation that can execute the project.
Thirdly, the federal government overlooked the two observations above and signed the PPA as guarantor five days before the
outcome of the expert opinion-World Bank report (Jus Mundi., 2022). This is a major deviation from standard project
procurement process. A major tool/technique used in the first two process according to PMBOK (2017) as shown in figure 1 is
INTERNATIONAL JOURNAL OF LATEST TECHNOLOGY IN ENGINEERING,
MANAGEMENT & APPLIED SCIENCE (IJLTEMAS)
ISSN 2278-2540 | DOI: 10.51583/IJLTEMAS | Volume XIV, Issue III, March 2025
www.ijltemas.in Page 378
expert opinion. The litigation, and other financial loss would been avoided if the expert opinion on the procurement process was
considered before the signing (Enron v. Nigeria and others , 2012; Forbes Media, 2004). About nine years before the ENPH
project in Nigeria, the government of India waited for the world bank report in Enron electricity project that was excecuted and it
gave them a better negotiating power compered with what Enron was proposing (Coburn, 2021). This shows that, there is a
massive gain in the used of expert judgment - World Bank as expert in India Enron project as stipulated by the procurement
process in figure 1.
The study further compared the model used in ENPH project with procurement process as shown in figure 1 and 2 by Project
Management Institute (2013) and PMBOK (2017)-see appendix 1.
Though, there could be several observations from this comparison, the study noted the following;
1. Procurement Planning: This a point of decision making, where there is determination of what to procure and when to
identifying potential seller. The decision on whether to source from internal or external is determined at this stage. Proper
procurement planning leads to the development of some documents such as risk register all the expected risk and how to respond
to them, the impact to the business if the risk should occur which is monetary value, the probability of its occurrence, the risk
owner(s), which would have helped to identify and analyze all the risk attached to the project and this would have spotted the risk
in high cost planned to be charged by Enron. The development of Cost Estimates for each activity is to determine bid
reasonableness from potential sellers. In ENPH project the essence of seeking external source is right according to Make-or-buy
analysis as tools & techniques used in procurement planning, at this point Nigeria could not generate enough electricity for its
consumer this is why ENPH became option, though sourcing is important but the action to choose only ENPH negates the
standard of procurement process.. Effective procurement planning helps in the management of public resources. Expert judgment
in this regards is the World Bank but the PPA has already been signed before the Expert judgment reports came, because of this
very action the Nation experience financial waste in millions of dollars for law suit on breach of agreement, on this note Expert
judgment review should not be overruled.
2. Solicitation Planning: This section allows prospective sellers to compete for project, it was observed that ENPH project did not
go through this route, sole sourcing was used which is against the standard. Procurement Standard Operating Procedures (SOP)
by International criminal court explained the rules to sole sourcing some of it are: it is that the identical products and services
have been obtained competitively within a reasonable period and the prices and conditions offered remain competitive, Within a
reasonable prior period, a formal solicitation has not produced satisfactory results, The value of the procurement is below the
monetary threshold established for formal methods of solicitation. Competitive bidding is to get quotation from other prospective
sellers from which the best will be picked that will meet up with what is required technically, financially etc. and the project
would have added to infrastructural development of the Nation.
3. Solicitation: Is the process of seeking information, proposals, and quotations from suppliers. ENPH project was not advertised
neither was the company in existing list of potential sellers. They came in by showing interest to Lagos State Government through
letter in June 19, 1999. Solicitation documents will vary greatly depending on the procurement method chosen. There is
discrepancy as to how Enron cam to Nigeria, two scenario were analysed. In both versions, International standard of international
competitive bidding (ICB) practices were overlooked and the deal was negotiated within months (Anton, 2012). This is the
activities that is expected to be performed by Procurement Managers where they either select from the data base of available
supplier or put out advert to enable interested bidder to bid for the project (Olabode, 2022).
The use of advert creates room for Competitive bidding with set of procedures which is designed to ensure fair and healthy
competition for World Bank-funded economic opportunities, which would have helped the economic growth or advancement
which involves the generation of wealth that is found in the benefit and advancement of society. And also covers the opportunities
such as economic development and job creation, and the wider social and environmental benefits.
4. Source Selection: Potential sellers are selected through application of the evaluation criteria. ENPH project involves
submission of proposal to the Government but did not participate in other aspect such as evaluation criteria, screening system etc
which are crucial to a project. The procuring organisation may prepare its own estimates as a check on proposed pricing.
Independent estimates are often referred to as “should cost” estimates. Procurement is often carried out by staff who lack relevant
training on Independent estimates (Shwarka & Anigbogu, 2012). Selection of appropriate potential seller among the proposal
through competitive bid would have made the Nation get the best offer, the financial waste of resources used in settling debt
would have been avoided.
5. Contract Administration: The seller must ensure that what is stated in the contract agreement is fully executed. ENPH's project
performance did not meet their contractual requirement. By December 31, 2000, Phase II of the project should have been
completed including possession of a plant site, all necessary easements from Lagos State and Nigeria, and a security letter of
credit. ENPH was authorized to seek independent “financing for at least 70 percent of the full capital costs” of the onshore power
plant, pipeline, and other Phase II facilities. The parties were bound to use all reasonable efforts to ensure that the conditions were
timely satisfied. As at December 31, 2000 which is the deadline for satisfying Phase II conditions, it passed without any effort by
Enron to meet those conditions. Enron could not perform its contractual obligation as a result of financial incapability, because of
these issues, a knowledge of procurement is needed to identify who can deliver as at when due (Olabode, 2022). Under contract
INTERNATIONAL JOURNAL OF LATEST TECHNOLOGY IN ENGINEERING,
MANAGEMENT & APPLIED SCIENCE (IJLTEMAS)
ISSN 2278-2540 | DOI: 10.51583/IJLTEMAS | Volume XIV, Issue III, March 2025
www.ijltemas.in Page 379
administration seller’s performance should meets contractual requirements and Enron failed in this aspect. Effective contract
administration helps in getting value for money and ensure fit for purpose.
6. Contract Close-out: It is the final phase of project before handling over. A well-managed closeout is one of the biggest factors
determining if a project finishes on time and on budget and how likely a client is to come back for repeat business. There was
already issues with the contract so the project did not get to this point. It was observed that ENPH project remains abandoned
project aside the huge debt it imposes on the Nation.
Specific Observation
i. Based on Objective One and Research Question One: A single Source or sole sourcing was used without following the
condition required for its used. This reduced the negotiating power of the owner of the project-Lagos State Government and the
input of the guarantor-Nigeria. This is a major lapse in procurement process.
ii. Based on Objective Two and Research Question Two: A comparison of what transpired as shown in figure 1 and table 1
shows that none of the procurement process was considered. This maybe because there was no procurement act as at the time of
the ENPH PPA and/or the haste with which the actual process was done as shown in Table 1. Thus Expert judgment was not
considered in the PPA signed
iii. Based on Objective Three and Research Question Three: Though the scope of this study did not cover the procurement
Acts that have been enacted from the lessons from the ENPH project’s procurement process, the subsequent cases like the P&ID
case shows that there are still lapses in the procurement act of 2007 that required amendment. Thus, if the procurement act is not
adequately review to address these lapses, the possibility of vendors taken advantage as done by P&ID, ENPH and so many other
will not abate. The lapse in ENPH project caused the Nation’s financial waste in millions of dollars for law suit on breach of
agreement which would have been averted if there has been proper procurement planning, ENPH project would have enormously
influence the economic growth as stated by Olabode 2018 (Nation’s electricity capability is one of the instrument for measuring
economic growth) and infrastructural development of the Nation
V. Conclusion
The findings shows that the procurement process in ENPH project is not in line with international standard as stated by World
Bank, there are core principles of procurement ranging from Value for money, economy, Integrity, fit for purpose, efficiency,
transparency and fairness, the contract negate all the core principles. ENPH project shows the use of sole sourcing but the rule
and regulation to it were not observed according to Procurement Standard Operating Procedures (SOP) by International criminal
court in the used of sole sourcing the following rule must apply offers for identical products and services have been obtained
competitively within a reasonable period and the prices and conditions offered remain competitive, within a reasonable prior
period, a formal solicitation has not produced satisfactory results etc Prior to 1999, Procurement by government and its agencies
were governed by Finance (Control and Management) Act, 1958, together with the Financial Regulations with basic rules for
managing public spending with set objectives which negate ENPH project. The use of procurement processes could have saved
Nigeria of the embarrassment and financial waste of eleven million dollars that have risen to twenty-two million dollars as at
2020, the project was expected to bring economic growth and infrastructural development to the Nation but failed due to poor
procurement process.
Recommendations
Based on the above findings, the following recommendations were made and are as follows:
1. Core principles of sole sourcing should be use if it should be adopted or adapted in any procurement process to improve the
negotiating power of the project owner.
2. Though delay in project delivery should be discouraged, decisions makers should not make hasty decision before seeking for
Expert judgment or show to the vendor a desperate emotion even when a vendor service is seriously required. Enron took
advantage of the desperation of Lagos State and came up with an agreement which was not properly studied until when it was
late.
3. The 2007 procurement act should be adequately review by procurement expert to address the lapses that could cause further
litigations
Contribution to Knowledge
In general, the study has been able to show that effective procurement can be used to reduce the number of litigations the country
is exposed to.
References
1. Adewoyin, A.A. (2023). The strategies of Lagos state public procurement agency for implementation of public
procurement law
2. Anton, E. & Katharine, N. G. (2012). Light Inside: The Experience of Independent Power Producers in Nigeria
INTERNATIONAL JOURNAL OF LATEST TECHNOLOGY IN ENGINEERING,
MANAGEMENT & APPLIED SCIENCE (IJLTEMAS)
ISSN 2278-2540 | DOI: 10.51583/IJLTEMAS | Volume XIV, Issue III, March 2025
www.ijltemas.in Page 380
3. Audu, A. O. (2018). Examine the Effects of Internal Control System on the Growth and Development of ECO Bank
Nigeria Limited. College of Management and Social Sciences, Business Administration. Lokoja: Salem University,
Lokoja, Nigeria. Retrieved from https://salemuniversity.edu.ng/wp-content/uploads/2022/01/Audu-Abel-Ojodomo-
Project-1.pdf
4. Bassey, U. (2018). EXCLUSIVE: Nigeria in Big Trouble as N2.7 Trillion Fine Threatens Collapse of Economy. Nigeria:
The Premium Times. Retrieved from https://www.premiumtimesng.com/news/headlines/269541-exclusive-nigeria-in-
big-trouble-as-n2-7-trillion-fine-threatens-collapse-of-economy.html?tztc=1
5. Benington, J. & Moore, M. (2011). Public Value: Theory and Practice. Basingstoke: Macmillan.
6. Bondarenko, P. (2024). Enron scandal: United States History. (J. E. Luebering, Editor, & Britannica) Retrieved from
https://www.britannica.com/event/Enron-scandal/additional-info#history
7. Center for Ethical Organizational Cultures. (2023). Enron: Not Accounting for the Future. Alabama: Auburn University.
Retrieved from https://www.google.com/search?client=firefox-b-d&q=Auburn+University
8. Cerna, L. (2013). The Nature of Policy Change and Implementation: A Review of Different Theoretical Approaches.
Retrieved April 21, 2018, from OECD Web site:
http://www.oecd.org/education/ceri/The%20Nature%20of%20Policy%20Change%20and%20Implementation.pdf
9. Clowes, W. (2021, September 15). Revived Enron Unit Loses Appeal to Claim Nigerian Yacht Proceeds. Retrieved from
https://www.bloomberg.com/news/articles/2021-09-15/revived-enron-unit-loses-appeal-to-claim-nigerian-yacht-
proceeds
10. Dávid-Barrett, E., & Fazekas, M. (2019, June 16). Grand Corruption and Government Change: an Analysis of Partisan
Favoritism in Public Procurement. European Journal on Criminal Policy and Research, 26, 411430.
doi:10.1007/s10610-019-09416-4
11. Edomah, N., Foulds, C., & Jones, A. (2016). Energy transitions in Nigeria: The evolution of energy infrastructure
provision (18002015). Open Access Energy Research, Engineering and Policy Journal, 9(10), 50-62.
12. Elizabeth, L. (2023). How to streamline your procurement processes.
13. Enron Nigeria Power Holding LTD Appellee V. Federal Republic of Nigeria Appellant, 15-7121 (United States Court of
Appeals, District of Columbia Circuit. December 27, 2016). Retrieved from https://caselaw.findlaw.com/court/us-dc-
circuit/1762983.html
14. Enron v. Nigeria and others , 14417/EBS/VRO/AGF (International Chambber of Commerce Novermber 19, 2012).
Retrieved from https://jusmundi.com/en/document/decision/en-enron-nigeria-power-holding-enph-v-federal-republic-of-
nigeria-final-award-monday-19th-november-2012#decision_5262
15. Folorunso, O., & Olowu, T. O. (2014). The Nigerian power system till date: A review. International Journal of Advance
Foundation and Research in Science & Engineering, 1(5), 20-33.
16. Ggenga-Ogundare, Y. (2022). Building collapse: Is Nigeria enacting adequate laws or suffering from breach in
implementation? Ibadan: Nigeria Tribune Newspaper Ltd. Retrieved from https://tribuneonlineng.com/building-collapse-
is-nigeria-enacting-adequate-laws-or-suffering-from-breach-in-implementation/
17. Hawkins, J. (2020). One Hundred Years Ago. The Book That Inspired the Carbon Price: Pigou’s The Economics of
Welfare. History of Economics Review, 77(1), 61-74.
18. Ikem, O. (2022, June 2). Tinubu Resurrects Enron and I travel down Memory Lane. Retrieved from
https://ikemsjournal.com.ng/tinubu-resurrects-enron-and-i-travel-down-memory-lane/
19. Jenkins, A. (2024, April 4). What Is Procurement? Types, Processes & Technology. Retrieved from
https://www.netsuite.com/portal/resource/articles/accounting/procurement.shtml
20. Julie, Y. (2023). What Is Procurement? Retrieved from https://www.investopedia.com/terms/p/procurement.asp
21. Jus Mundi. (2022, March 28). Enron v. Nigeria and others . (N. Y. Law.com, Producer, & Forbes) Retrieved from
https://jusmundi.com/en/document/decision/en-enron-nigeria-power-holding-ltd-v-1-lagos-state-government-2-federal-
republic-of-nigeria-3-power-holding-company-of-nigeria-order-of-the-united-states-supreme-court-denying-petition-for-
a-writ-of-certiorari-mon
22. Kalu, I. N., Eme, U. O., Ezekwe, A. C., & Oti, C. A. (2020). Public Procurement Policy and the Nigerian Political
Economy. ResearchGate. Retrieved from https://www.google.com/url?sa=t&source=web&rct= j&opi=89978449&url=
https://www.researchgate.net/profile/Kalu-Ndu/publication/344899768 PUBLIC PROCUREMENT POLICY AND THE
NIGERIAN POLITICAL ECONOMY By KALU INNOCENT NDU PhD FISMN MNIMN DEPARTMENT OF
MARKETING
23. Karan, K. (2024). What Is Procurement? Your Ultimate Guide to the Process, Strategies, and Automation.
24. Kelvin, G., Moisob, A., & Graham, B. (2021). The Impact of Organizational Culture on Public Procurement Act
Compliance in Obuasi Municipality. World Journal of Advanced Research and Reviews, 12(3), 187199.
doi:10.30574/wjarr.2021.12.3.0489
25. Levin Center. (2021, December 10). Portraits in Oversight: Congress and the Enron Scandal. Wayne State Law School.
Retrieved from https://www.levin-center.org/wp-content/uploads/2021/12/10-Portraits-in-Oversight-Congress-and-the-
Enron-Scandal-Levin-Center-at-Wayne-Law.pdf
26. Marijn, O. (2024). Procurement Process: Master 7 Essential Steps in 2024.
27. Masoud, Y., Emmanuel, T., & Salum, M. (2021). The Effect of Internal Auditing on Procurement Performance in
Parastatal Organizations of Tanzania. Business Education Journal, 10(3). Retrieved from
INTERNATIONAL JOURNAL OF LATEST TECHNOLOGY IN ENGINEERING,
MANAGEMENT & APPLIED SCIENCE (IJLTEMAS)
ISSN 2278-2540 | DOI: 10.51583/IJLTEMAS | Volume XIV, Issue III, March 2025
www.ijltemas.in Page 381
file:///C:/Users/NCC%20PROJECT%202020/Downloads/THE_EFFECT_OF_INTERNAL_AUDITING_ON_PROCUR
EMENT_PER.pdf
28. Mohammed, I.L., Ameenah, H. A., & Yahaya, A. (2022). Most Critical Effects of Non-Implementation of Public
Procurement Policy on Construction Projects Delivery in Nigeria. Journal of Applied Ecology and Environmental
Design JAEED2022 [3279-8992] Vol.22
29. Momodu, A. S. (2010). Application of system dynamics for decision making in Nigeria's eletic power system. Beigin a
Thesis Proposal Subnitted in Partial Fulfillment of the Requirment for the Award of the Degree of Doctor of Phylosoply
in Technology Management, Obafemi Awolowo University, Technology Planning and Development, Faculty of
Technology.
30. Moore, M. H. (1995). Creating public value: Strategic management in government. Harvard university press
31. Moses, A. I. (2019). Empirical Analysis of Forensic Accounting Techniques in Curbing Creative Accounting in Nigeria.
School of Postgraduate Studies, Department of Management Sciences. Lokoja: Salem University, Lokoja. Retrieved
from https://salemuniversity.edu.ng/wp-content/uploads/2022/01/MOSES-AGUVA-PROJECT.pdf
32. Muraina, A., Enyinna, O., & Stella, I. (2010, June). Transparency in Corporate Governance: A Comparative Study of
Enron, USA and Cadbury PLC, Nigeria. The Social Sciences, 5(6), 471-476. doi:10.3923/sscience.2010.471.476
33. Nnamani, C. (2023). What State-Generated Electricity could mean for Nigerians and Local Tech Ecosystems.
TechCabal. Retrieved from https://techcabal.com/2023/03/23/state-generated-electricity-power-tech-ecosystem/
34. Odhiambo, W., & Kamau, P. (2003). Public Procurement: Lessons from Kenya, Tanzania and Uganda. OECD
Development Centre Working Papers 208. Retrieved from https://ideas.repec.org/p/oec/devaaa/208-en.html
35. OECD. (2019). Government at a Glance. Retrieved from https://www.oecd.org/governance/govataglance.htm
36. Okoye, E., & Gbegi, D. (2013, March). An Evaluation Of The Effect Of Fraud And Related Financial Crimes On The
Nigerian Economy. Kuwait Chapter of Arabian Journal of Business and Management Review, 2(7), 81-92.
37. Olabode, S. O. (2018, Febuary). Technological Innovation and Public Private Partnership: Implications on
thePerformance of Nigeria Electric Power Sector. Doctor of Philosophy in Management Thesis, 1. Ojo, Lagos, Nigeria:
Lagos State University .
38. Olawale, O. (2004). Nigeria: Enron Fall-Out: I'm Vindicated, Says Ex-Lawmaker. Apapa: This Day. Retrieved from
https://allafrica.com/view/publisher/editorial/editorial/id/00010349.html
39. Olukoju, A. (2003). Chapter two. Electricity supply in Lagos, 1898-2000. In A. Olukoju, Infrastructure Development
and Urban Facilities in Lagos, 1861-2000 (pp. 21-45). Ibadan, Oyo, Nigeria: IFRA-Nigeria, Institut français de
recherche en Afrique. doi:10.4000/books.ifra.814
40. Olusola, A. O. (2022, April). Effects of Audit Fees among Quoted Firms in Nigeria: An Audit Quality Perspective.
International Journal of Advances in Engineering and Management (IJAEM), 4(4), 842-854. doi:10.35629/5252-
0404842854
41. Organisation for Economic Co-operation and Development-OECD. (2021). Fair Market Conditions for Competitiveness
in the Adriatic Region (Policy Briefing Note): The OECD Public Procurement Principles. Global Relations-South East
Europe. Retrieved from https://www.oecd.org/south-east-europe/programme/OECD-Public-Procurement-Policy-
Briefing-Note.pdf
42. Owiti, J. O. (2022). Effectiveness of Construction Contract Procurement Processes in Public Projects In Kenya: A
Survey of County Government Projects. Jomo Kenyatta University of Agriculture & Technology, Department of
Construction Project Management. Online: ResearchGate. doi:10.13140/RG.2.2.29251.68643
43. Owolabi, F. (2020). EXCLUSIVE: Nigeria’s Foreign Assets at Risk as Enron seeks to Enforce $22m Arbitration Award.
TheCable. Retrieved from https://www.thecable.ng/exclusive-nigeria-risks-foreign-assets-as-enron-seeks-to-enforce-
22m-arbitration-award
44. Parestico, P. (2019, Novermber 4). Inter-Governmental Relations and Procurement Non-Compliance in African Local
Government Systems. Journal of Public Procurement 4 November 2019, 19(4), 277-294. doi:
https://doi.org/10.1108/JOPP-01-2019-0001
45. PMBOK. (2017). A Guide to the PROJECT MANAGEMENT BODY OF KNOWLEDGE (Sixth ed.). Newtown Square,
Pennsylvania: Project Management Institute, Inc. Retrieved from
https://www.grf.bg.ac.rs/p/learning/pmibok_vodic_6_to_izdanje_1622030936944.pdf
46. PMI. (2000). A Guide the Project Management Body of Knowledge. Newtown Square PA, USA: American National
Starndard/Project Management Institute.
47. Project Management Institute. (2013). A Guide to the Project Management Body of Knowledge (PMBOK® Guide)
(Fifth ed.). Newtown Square,, Pennsylvania , USA: Project Management Institute, Inc.
48. Robert, E. L., & Clifford, P. M. (2004). What is Public Procurement? Definitional Problems and Implications.
International Public Procurement Conference Proceedings,, III. Retrieved from
https://www.researchgate.net/publication/237538383 WHAT IS PUBLIC PROCUREMENT DEFINITIONAL
PROBLEMS AND IMPLICATIONS
49. Rajesh, K. & Verner, W. (2011). Negotiating in India: Some Case Studies
50. Saeed, S., & Chunlin, X. (2019, October). Public Procurement. Living reference work entry, 1-8. doi:10.1007/978-3-
319-31816-5_344-1
51. Shubik, M. (1970). A curmudgeon's guide to microeconomics. Journal of Economic Literature, 8(2), 405-434.
INTERNATIONAL JOURNAL OF LATEST TECHNOLOGY IN ENGINEERING,
MANAGEMENT & APPLIED SCIENCE (IJLTEMAS)
ISSN 2278-2540 | DOI: 10.51583/IJLTEMAS | Volume XIV, Issue III, March 2025
www.ijltemas.in Page 382
52. Silas, K. G. & Sammy, O. (2022). Effect of Public Procurement reforms on Performance of Meru County Government,
Kenya. International Journal of Economics, Commerce and Management, United Kingdom.
53. Sope, W. (2015). A comparative analysis of the Nigerian public procurement act against international best practice
54. Stuart,G. & John, D.M (2011). Corporate Governance Post-Enron: Effective Reforms, or Closing the Stable Door?
55. Thairu, J., & Chirchir, M. (2016). Implementation of the Youth Preference and Reservations Policy in Public
Procurement: The Case of State-Owned Enterprises in Nairobi. International Journal of Supply Chain Management, 1(1),
1-18
56. Tim, T., & Luitzen, d. B. (2017). Public Procurement Reform in the EU: Start of a New Era? IMP Journal, 11(3), 431-
451. doi:10.1108/IMP-09-2015-0056
57. Ukpe, W. (2021, September 15). Enron Nigeria Power Holding Ltd loses case on proceeds of luxury Yacht. Retrieved
from https://nairametrics.com/2021/09/15/enron-nigeria-power-holding-ltd-loses-case-on-proceeds-of-luxury-yacht/
58. United States Court of Appeals for the district of Columbia circuit (2016). Enron Nigeria Power Holding, Ltd.V.Fed.
Republic Of Nigeria 844 F.3d 281 (D.C. Cir. 2016) Decided Dec 27, 2016 Appeal from the United States District Court
for the District of Columbia (No. 1:13-cv-01106)
59. Watkins, T. (2006). The Rise and Fall of Enron. San José State University, Department of Economics. San José: Silicon
Valley & Tornado Alley. Retrieved from https://www.sjsu.edu/faculty/watkins/enron.htm
60. Will, K. (2024). Memorandum of Understanding (MOU) Defined, What's in It, Pros/Cons, MOU vs. MOA
61. Williams, L. & Shearer, H. (2011). Appraising public value: Past, present and futures.
62. World Bank. (2016). Procurement in World Bank Investment Project Financing: Review of Results After Five Years of
Implementation of the Procurement Framework - FY17 to FY21. Retrieved from
https://projects.worldbank.org/en/projects-operations/products-and-services/publication/procurement-in-world-bank-
investment-project-financing-review-of-results-after-five-years-of-implementation
63. World Bank. 2020. Work Bank Procurement Framework and Business opportunities
64. Yussuf, M. (2023, March). The Effects of Political Interference on Procurement Performance in the Parastatal
Organizations in Dar es Salaam Region. Research in Business & Social Science, 12(2), 158-169.
doi:10.20525/ijrbs.v12i2.2419