Page 874
www.rsisinternational.org
INTERNATIONAL JOURNAL OF LATEST TECHNOLOGY IN ENGINEERING,
MANAGEMENT & APPLIED SCIENCE (IJLTEMAS)
ISSN 2278-2540 | DOI: 10.51583/IJLTEMAS | Volume XV, Issue IV, April 2026
Temporary Transformer Room Installations for Construction Sites:
Cable Sizing, Testing, WR2, and Circuit Breaker Discrimination
Ir. Dr. Samuel Kwok Piu LIP
1
, Dr. Wing Cheung TANG
2
, Ir. Jonathan WONG
3
1
Founder and Managing Director of Lordray Engineering Company Limited
2
Adjunct Professor of Spectrum International University College, Malaysia
3
General Manager of Paul Y. (E&M) Contractors Ltd
DOI:
https://doi.org/10.51583/IJLTEMAS.2026.150400079
Received: 08 April 2026; Accepted: 13 April 2026; Published: 12 May 2026
ABSTRACT
Large-scale construction sites frequently require electrical power exceeding the capacity of a single 400A three-
phase feeder. In such contexts, power utilities typically supply a small-capacity 11kV transformer (e.g., 200–300
kVA) housed within a purpose-built temporary transformer room. This paper examines the practical engineering
considerations surrounding the construction of such temporary transformer rooms, with particular attention to
design specifications for weatherproofing, oil containment, ventilation, and security. Beyond physical
infrastructure, the paper addresses essential technical procedures including cable sizing in accordance with the
EMSD Wiring Code, the role of the Registered Energy Assessor (REA) under Cap. 610, testing and
commissioning (T&C) protocols, periodic inspection and testing (WR2), and the critical engineering task of
circuit breaker discrimination. Drawing on authentic field experience from Hong Kong construction sites, this
paper aims to share practical knowledge with industry peers, highlighting both technical requirements and
common pitfalls that may lead to financial losses, regulatory non-compliance, or safety hazards. The paper
concludes that early engagement of qualified professionals, rigorous adherence to testing protocols, and
systematic verification of protective device coordination are essential to successful temporary electrical
installations.
Keywords: building energy code, cable sizing, circuit breaker discrimination, temporary transformer room,
testing and commissioning, WR2
INTRODUCTION
The delivery of reliable temporary electrical power to large-scale construction sites presents unique engineering
challenges that differ significantly from permanent building installations. Construction sites (Development
Bureau, 2024) are dynamic environments characterized by rapidly changing load profiles, exposure to weather
elements, and the need for rapid deployment and eventual removal of electrical infrastructure. Unlike permanent
installations, which benefit from dedicated electrical rooms within building structures, temporary transformer
rooms must be self-contained, weather-resistant, and capable of safe operation in outdoor environments for the
duration of construction activities.
In Hong Kong, power utilities such as CLP Power (2025) and Hongkong Electric (HKE) provide temporary
high-voltage (11kV) transformers to large construction sites where the power demand exceeds the capacity of
standard low-voltage feeders. A typical temporary transformer installation may range from 200 kVA to 300 kVA,
housed within a custom-fabricated metal room. The design, construction, testing, and ongoing maintenance of
these installations must comply with multiple regulatory frameworks, including the EMSD (2025) Wiring Code,
Cap. 610 Building Energy Efficiency Regulation (2013), the Building Energy Code (BEC), and safety
regulations administered by the Labour Department and the Construction Industry Council (CIC).
Page 875
www.rsisinternational.org
INTERNATIONAL JOURNAL OF LATEST TECHNOLOGY IN ENGINEERING,
MANAGEMENT & APPLIED SCIENCE (IJLTEMAS)
ISSN 2278-2540 | DOI: 10.51583/IJLTEMAS | Volume XV, Issue IV, April 2026
This paper synthesizes practical field experience from multiple construction projects in Hong Kong, including
the authors' direct involvement in the design, construction, testing, and commissioning of temporary transformer
rooms. The objectives of this paper are threefold:
1. To document best practices for the physical construction of temporary transformer rooms, including plinth
design, oil containment, ventilation, weatherproofing, and security features.
2. To explain the technical procedures for cable sizing, testing and commissioning (T&C), periodic inspection
(WR2), and circuit breaker discrimination.
3. To highlight the regulatory requirements under Cap. 610, including the critical role of the Registered
Energy Assessor (REA) and common compliance pitfalls that can lead to substantial financial losses.
It is important to note that this paper is written from the perspective of practicing engineers sharing experiential
knowledge. While the paper draws on established codes and standards, it does not claim to provide exhaustive
technical specifications. Readers are strongly advised to consult the latest editions of all referenced codes and
regulations before undertaking any electrical installation work.
Construction of Temporary Transformer Room
Rationale for Temporary Transformer Rooms
Tower cranes, concrete batching plants, dewatering pumps, welding equipment, site offices and lighting all need
a lot of electricity on large construction sites, especially for infrastructure projects like railway extensions, tunnel
constructions and major building developments. A standard low-voltage feeder (like a 400A three-phase) is not
always enough for these needs. In this case, the power company provides a small 11kV transformer, usually rated
between 200 kVA and 300 kVA, that lowers the voltage from high to low (380V/415V) for distribution across
the site.
To keep the transformer and its medium-voltage (MV) panel safe from rain, dust, unauthorised access, and
accidental contact, they must be kept in a weatherproof, secure enclosure. This is the temporary room for the
transformer. The authors note that the installations done by CLP Power and the equipment made by Merlin Gerin
(now part of Schneider Electric) are typical, but there is a lot of variation between suppliers.
Structural Design and Materials
The authors say that the temporary transformer room is usually made of painted mild steel to keep it from rusting.
The building needs to be strong enough to handle wind loads, hits from construction vehicles by accident, and
normal site activities.
Figure 1: Typical temporary outdoor transformer room
Page 876
www.rsisinternational.org
INTERNATIONAL JOURNAL OF LATEST TECHNOLOGY IN ENGINEERING,
MANAGEMENT & APPLIED SCIENCE (IJLTEMAS)
ISSN 2278-2540 | DOI: 10.51583/IJLTEMAS | Volume XV, Issue IV, April 2026
Figure 1 shows a typical temporary outdoor transformer room. The room is big enough for a small oil-type
transformer (like a 200 kVA, 11kV) and an MV panel. It's important to note that control circuit instruments are
often housed in a separate cabinet outside the transformer room, on the right side of transformer room. The
authors say that this separation makes it less necessary for people to go into the transformer room to keep an eye
on things and control them, which makes things safer.
The manuscript talks about pictures that are not in the text that is available. Future editions ought to include
these images to enhance the descriptive material.
Plinth and Oil Containment
The transformer room needs to be built on a concrete base that is at least one foot (about 300 mm) above the
ground. This elevation has two purposes: first, it keeps water from getting into the ground during heavy rain;
second, it gives the heavy transformer a stable, level base.
A very important safety feature is the four-inch (about 100 mm) high curb that goes around the outside of the
plinth. This way, the oil does not spill onto the pavement outside. If oil-filled transformers leak, they can be bad
for the environment because they hold a lot of insulating oil. The kerb serves as a secondary containment bund,
stopping spilt oil from getting to the ground or drainage systems around it. This design feature is in line with
environmental protection rules that say you cannot dump oil into stormwater drains or natural bodies of water.
Weatherproofing and Ventilation
Because construction sites are outside, temporary transformer rooms need to be very weatherproof. The roof is
made of metal sheets, and the eaves go beyond the room's footprint. This overhang keeps rainwater from falling
directly into the room.
The roof metal sheet eave of the transformer room goes out from the top of the room to keep rainwater from
dripping down from the roof into the transformer room (see Figure 2).
Figure 2: Concrete plinth provided with 4 inches high kerb
Page 877
www.rsisinternational.org
INTERNATIONAL JOURNAL OF LATEST TECHNOLOGY IN ENGINEERING,
MANAGEMENT & APPLIED SCIENCE (IJLTEMAS)
ISSN 2278-2540 | DOI: 10.51583/IJLTEMAS | Volume XV, Issue IV, April 2026
Ventilation is necessary to get rid of the heat that the transformer makes while it is working. There are ventilation
fans on the roof, but they need to be protected from rain. The authors talk about a certain design solution:
The dog house has a top canopy that covers the fan, so rainwater cannot get into the transformer room through
the fan from above. Ventilation air goes out from the side. This design lets hot air out while keeping rainwater
from coming in directly. Here are some more weatherproof features:
1. Ventilation louvres on all sides, with fine wire mesh to keep out bugs, birds, and other things.
2. Doors that can be locked on all sides of the room so that workers can get to all sides of the transformer
and MV panel (keeping in mind that the space inside is limited).
3. Doors that swing open and closed with locks, metal louvres, and fine-hole wire mesh to keep rain from
getting in from the side.
The dog house ventilation design is a cheap but effective way to solve a common problem with outdoor electrical
enclosures. Engineers who are designing similar installations in tropical or subtropical areas should think about
using or changing this method.
Security and Access Control
There are live high-voltage and medium-voltage equipment in the transformer room. To keep people from getting
in without permission, all doors must be locked.
Figure 3: Control panel is mounted outside of transformer room
The control panel is often mounted outside (see Figure 3) so that it can be monitored and operated without having
to go into the transformer room. The fused switches and moulded case circuit breakers (MCCBs) that carry heavy
currents, on the other hand, must stay in the locked room. These outgoing power supply switches are heavy
current rating and are live and must be installed inside transformer room and all doors are locked against
unauthorized entry. This setup strikes a good balance between ease of use and security needs.
Site Context and Integration
Figure 1 shows a large construction site that is well-organised and has hoarding structures supported by I-beams
on concrete plinths. There are noise barrier cloths set up high all around the site, and the boundary hoarding has
walking platforms with company advertisement canvases on them. This picture puts the transformer room in the
context of the whole construction site, which shows how important it is to connect it to safety and security
measures on the site.
The authors give a very useful piece of advice "Good site formation". The transformer room must be placed
carefully within the site layout, considering how easy it will be to get to for delivery, maintenance, emergency
Page 878
www.rsisinternational.org
INTERNATIONAL JOURNAL OF LATEST TECHNOLOGY IN ENGINEERING,
MANAGEMENT & APPLIED SCIENCE (IJLTEMAS)
ISSN 2278-2540 | DOI: 10.51583/IJLTEMAS | Volume XV, Issue IV, April 2026
response, and eventual removal. Bad placement can cause problems with operations, higher costs, and safety
risks.
Cable Sizing According to EMSD Wiring Code
Overview of the Cable Sizing Process
For electrical safety and system performance, it is very important to get the right size cable. Cables that are too
small can overheat, which can damage the insulation, cause copper losses, lower the voltage, and even start a
fire. Oversized cables are safe, but they cost too much and are hard to install and end.
The most recent version of the EMSD (2025) Wiring Code gives a clear way to size cables that must be followed
for all permanent and temporary installations. There are three main steps in the process:
(1) estimating the load and calculating the maximum demand,
(2) applying correction factors, and
(3) checking the current-carrying capacity and voltage drop.
Step 1: Maximum Demand Calculation
The maximum demand current of the circuit is the first thing to think about when sizing a cable. The designer
must figure out the expected steady-state operating current for a final circuit that will power a specific load, like
a tower crane, a welding set, or a lighting distribution board. When choosing a protection device, you need to
keep in mind that starting currents for motor loads can be much higher than running currents. This is because
cables can handle short bursts of overload without being damaged.
Step 2: Application of Correction Factors
The designer needs to divide the maximum demand current (Ib) by the product of the relevant correction factors
to get a "reference current" (It) for choosing the cable. The correction factors consider the installation conditions
that make the cable less able to carry current.
The EMSD Wiring Code says that the following correction factors are needed:
1. Grouping factor (Cg): Cables that are close together (like those that are bunched up trunking or buried
together) cannot get rid of heat as well as cables that are alone.
2. Thermal insulation factor (Ci): Cables that are buried in thermal insulation, like in insulated walls, don't
let heat escape as easily.
3. Ambient temperature factor (Ca): The higher the ambient temperature, the less current the cable can carry.
4. Soil thermal resistivity factor (Cs): The type of soil that buried cables are in affects how well they can
get rid of heat.
If you multiply the three correction factors together, you get 0.8. The final circuit's maximum demand is 20A,
so 20A/0.8 = 30A. This means that the cable must be able to carry at least 30A in normal conditions, like when
the temperature is 30°C and the air is free.
Step 3: Cable Selection from Tables
The designer uses the calculated reference current (It) to look up the right table in the EMSD (2025) Wiring
Code.
1. The type of insulation on the cable (PVC or XLPE, which stands for cross-linked polyethylene)
The material of the conductor (copper or aluminium)
2. How many phases are there (one or three)?
Page 879
www.rsisinternational.org
INTERNATIONAL JOURNAL OF LATEST TECHNOLOGY IN ENGINEERING,
MANAGEMENT & APPLIED SCIENCE (IJLTEMAS)
ISSN 2278-2540 | DOI: 10.51583/IJLTEMAS | Volume XV, Issue IV, April 2026
3. How to install it (surface mounted, in conduit, in trunking, buried direct, etc.)
The cable you choose must have an Itab that is equal to or greater than the It that is needed. For example, if you
choose a 4 sq mm cable, the current capacity is greater than 30A.
Step 4: Voltage Drop Verification
If the voltage drops between the supply point and the load is too high, a cable that meets current-carrying
requirements may still not be acceptable. The EMSD Wiring Code usually says that the voltage drop for lighting
circuits can be no more than 4% of the nominal supply voltage and for other power circuits, it can be no more
than 6%. However, the exact limits depend on the type of installation.
The calculation for the voltage drops depends on:
1. Length of the cable
2. Current (Ib)
3. Cross-sectional area of the conductor
4. Material for the conductor
5. The load's power factor
The EMSD Wiring Code has tables and formulas for how much voltage drops per ampere per metre. There is a
formula in the code to figure out the voltage drop. If the cable size meets both the current capacity and the voltage
drop, confirm that you want to use that size. If not, choose the next bigger size cable. Check the voltage drop
and current capacity again.
Practical Implications for Temporary Installations
When sizing cables for temporary construction sites, you also need to think about:
1. Requirements for mechanical protection (cables can be run on the ground, but they must be able to handle
vehicle traffic)
2. Moving temporary distribution boards around a lot
3. Bad weather (UV rays, moisture, and dust)
The basic calculations are the same as for permanent installations, but the correction factors and installation
methods may be very different. The authors stress that having a temporary status does not mean that installations
are not required to fully follow the EMSD (2025) Wiring Code.
Cap. 610 Energy Efficiency, and the Role of the Registered Energy Assessor (REA)
Overview of Cap. 610 and the Building Energy Code (BEC)
Cap. 610 of the Laws of Hong Kong (2013), formally titled the Building Energy Efficiency Regulation, came
into effect after 2010. This regulation mandates that certain building services installations comply with the
prescribed Building Energy Code (BEC). The BEC sets minimum energy efficiency standards for four key
systems:
Electrical installations (EE-EL form)
Air conditioning installations (EE-AC form)
Lighting installations (EE-LG form)
Lift and escalator installations (EE-LE form)
Page 880
www.rsisinternational.org
INTERNATIONAL JOURNAL OF LATEST TECHNOLOGY IN ENGINEERING,
MANAGEMENT & APPLIED SCIENCE (IJLTEMAS)
ISSN 2278-2540 | DOI: 10.51583/IJLTEMAS | Volume XV, Issue IV, April 2026
For new building installations, and for certain "material change" or addition and alteration (A&A) works, the
owner must engage a Registered Energy Assessor (REA) to verify compliance with the BEC. The REA is a
professional (typically an electrical or mechanical engineer) registered with the Electrical and Mechanical
Services Department (EMSD) to carry out energy assessments.
The Copper Loss Requirement
One of the most important things that the building energy code (BEC) electrical section requires is that copper
losses in electrical circuits be kept to a minimum. Copper loss (I²R loss) is the heat that conductors give off
because they resist electricity. Too much copper loss wastes energy, makes the cooling loads heavier, and lowers
the overall efficiency of the system.
There are rules for limiting copper loss, usually less than 1% is okay for the final circuit, submain, and riser. The
exact percentage may change depending on the type of circuit and the use, but the basic idea is that designers
must choose cable sizes that keep resistive losses within set limits. Nowadays, usually excel sheets calculate the
copper loss, meaning that compliance calculations are usually done with spreadsheet tools that use the BEC
formulas (Electrical and Mechanical Services Department, 2024). But the manuscript does not say which
formulas or which version of the BEC to use, which makes it hard for readers who want to do the calculation
again.
The REA's Role and Common Compliance Failures
The registered energy assessor (REA) oversees checking the design (usually before construction starts) and
making sure that the installation is up to building energy code (BEC) standards. The manuscript stresses how
important it is to get involved in REA early:
You must get REA involved to check the design before construction starts. I saw a case in Kwun Tong where the
owner of a whole floor of shops was unhappy with BEC. All the shops could not be rented out to tenants, and
the owner lost a lot of money every day because they did not have any rent income.
This case shows an important point: under Cap. 610, the owner is legally responsible for BEC compliance. If the
REA does not find a problem with compliance, or if the owner tries to get around the REA process, the building
or property cannot be rented or occupied. This means big money losses for businesses that own commercial real
estate.
Exempted Items: A Lesson in Code Interpretation
The authors talked about the Kwun Tong case, which had to do with a finding of non-compliance with lighting
power density. I learned that the reason is that advertising lights have too much power and do not meet the code's
lighting power density requirement. I told the owner that the advertisement light power was for commercial use,
like a window display light, and that it was not subject to BEC. Then it passed BEC. The technical guide for
BEC has a list of exempt items with pictures and very clear instructions. Not clear what REA is or if it is an
exempt item; lighting power density must be higher than Code requirements; cannot pass BEC.
This example shows how important it is for REAs and designers to be very familiar with the BEC Technical
Guide (EMSD, 2024a), especially the list of items that are not subject to the rules. Lighting for advertising (like
shop window displays and illuminated signs) is often not included because it is used for branding rather than
general lighting. But if the REA does not know about this exemption, they might incorrectly mark a compliant
installation as non-compliant, which would slow down the project's completion.
The manuscript does not say which version of the BEC Technical Guide it uses or gives the exact clause numbers
for the advertising lighting exemption. Revisions in the future should have exact references.
Page 881
www.rsisinternational.org
INTERNATIONAL JOURNAL OF LATEST TECHNOLOGY IN ENGINEERING,
MANAGEMENT & APPLIED SCIENCE (IJLTEMAS)
ISSN 2278-2540 | DOI: 10.51583/IJLTEMAS | Volume XV, Issue IV, April 2026
Financial Implications of Non-Compliance
The manuscript gives a clear warning about the financial effects of not following BEC:
Whole floor shops cannot be rented out, which means a big loss of rental income. It loses million a month, so
hiring experienced ICE to check is not a good idea. It is not only dangerous, but it is also a big financial loss.
Engaging ICE is very cheap, but if you do not, the penalty for an accident is very high (a fatal accident means
the owner goes to jail for three years and pays a fine of 20 million dollars). You must go bankrupt right away
and go to jail.
While the author talks about "ICE" (the Institution of Civil Engineers), they probably mean "experienced
consulting engineer" in this case. The main point is that hiring experienced advisors is a false economy. Hiring
a qualified REA or consulting engineer is very cheap compared to the possible losses from delays in finishing a
project, not being able to rent out space, or fines from the government after an accident.
Limitations of the Regulatory Discussion
The original manuscript has a long and emotional discussion of dishonest employees, bad accountants, and court
cases. Although these observations are framed as aspects of the author's personal experience, they lack direct
relevance to the technical subject of temporary transformer rooms and electrical installations. For the sake of
this academic revision, we only note the author's claim that internal malpractice can make regulatory risks worse.
A more thorough examination would necessitate documented case evidence instead of anecdotal claims. Because
of this, the revised article does not include this material because it is not relevant to a technical engineering paper.
Testing and Commissioning (T&C) of Electrical Installations
Overview of T&C Requirements
Testing and commissioning (T&C) is the process of making sure that electrical installations are safe, work, and
meet design and regulatory standards. T&C must be done before the installation is powered up for normal
operation and again during regular inspections (WR2) for temporary transformer rooms and their distribution
systems. The manuscript enumerates the following critical T&C tests, each of which is analysed
comprehensively below.
Visual Inspection
People often do not check the actual items installed match what is shown in the drawings and specifications. The
engineer must check with their eyes that:
All the equipment, like cables, switchgear, transformers, and distribution boards, meets the approved plans and
specs.
The equipment is set up correctly, supported correctly, and is not physically damaged.
Clearances and work areas follow safety rules.
There are labels and ID tags that can be read.
Visual inspection can find problems that electrical testing alone might not, like the wrong type of equipment,
missing parts, or obvious mistakes made during installation.
Insulation Resistance Test (Megger Test)
Insulation resistance testing, often called the "Megger test" (Juris et al., 2024) after a well-known maker of
insulation testers, checks the resistance of insulation between conductors and between conductors and the ground.
Low insulation resistance means that moisture has gotten in, the material has been damaged, or there are
problems with how it was made that could cause leakage currents or short circuits.
Page 882
www.rsisinternational.org
INTERNATIONAL JOURNAL OF LATEST TECHNOLOGY IN ENGINEERING,
MANAGEMENT & APPLIED SCIENCE (IJLTEMAS)
ISSN 2278-2540 | DOI: 10.51583/IJLTEMAS | Volume XV, Issue IV, April 2026
To do the test, you apply a DC voltage (usually 500V, 1000V, or 2500V, depending on the system voltage) and
then measure the current that comes out. The EMSD (2025) Wiring Code says what values are okay. The
manuscript lacks specific acceptable values, presenting a limitation; readers are required to refer directly to the
Code.
Continuity Test
Continuity testing checks that all the conductors make a complete, low-resistance path from one end point to the
next. This test is very important for protective earth (PE) and bonding conductors because high resistance could
stop overcurrent protection devices from working properly during a fault.
Polarity Test
Polarity testing (Hora, 2024) shows that single-pole switching, and protective devices are connected to the line
conductor (not the neutral) and that socket outlets and other termination points are wired correctly (with the line,
neutral and earth in the right places). If the polarity is wrong, equipment can still be powered on even when it is
turned off, which is very dangerous.
Earth Fault Loop Impedance Test
The earth fault loop impedance (Zₛ) (Neamt, Neamt & Chiver, 2021) is the resistance of the path that fault current
takes from the point of fault back to the source (transformer) through the protective earth conductor. This
impedance must be low enough that, even when there is a fault, enough current flows to turn on the overcurrent
protective device in the time required to disconnect.
The test consists of measuring the loop impedance and making sure it doesn't go over the maximum value set
for the protective device (which is usually based on the device's time-current characteristic curve).
Earth Electrode Test
It is necessary to measure the resistance to earth for installations that use earth electrodes, such as earth rods or
foundation earth electrodes. The EMSD (2025) Wiring Code says what the highest acceptable values for earth
resistance are. High earth resistance can stop fault currents from spreading out properly and make touch voltages
dangerous.
Secondary Current Injection of Relays
To make sure that protection relays (like overcurrent relays and earth fault relays) work correctly at the current
and time settings they are set to, they must be tested. Secondary injection testing means taking the relay off its
current transformers (CTs) and sending test currents directly into the relay's input terminals.
All relays must be pulled out and tested with a portable big tester that can make current and measure the time it
takes for the relay to start and stop. Make sure that the current plug setting multiplier and time multiplier match
the graph on the relay for checking the tripping time.
Primary current injection (testing with full fault current through the CTs) is typically performed at the factory
due to the high currents required. Factory workers also do high-voltage pressure tests, like 2 kV.
Ductor Test of Busbar Joints (Micro Resistance)
To stop localised heating, busbar joints (the places where different sections of busbar connect) must have very
low resistance. A ductor tester (micro-ohmmeter) sends a high-test current (usually 50A to 600A) through the
joint and measures the voltage drop across it to figure out the resistance. A high resistance means that the joint
is loose or dirty and needs to be re-torqued or cleaned.
Page 883
www.rsisinternational.org
INTERNATIONAL JOURNAL OF LATEST TECHNOLOGY IN ENGINEERING,
MANAGEMENT & APPLIED SCIENCE (IJLTEMAS)
ISSN 2278-2540 | DOI: 10.51583/IJLTEMAS | Volume XV, Issue IV, April 2026
Tightness Torque Test of Bolts on Busbar
Bolted connections on busbars and cable terminations need to be tightened to the torque that the manufacturer
says to. If you tighten too much, the threads can strip or the conductors can break. If you do not tighten enough,
the resistance will be high, and the heat will build up. You can use a torque wrench to make sure that each bolt
is tightened to the right amount.
Cable Termination Verification
The manuscript stresses a simple but important principle to check and make sure that the ends of the cable and
wire are connected correctly, not wrong. Misconnections, like swapping phases, connecting neutral to earth, or
rotating three-phase motors the wrong way, can break equipment, make things unsafe, and cause problems with
how things work.
Functional Testing
Functional testing checks that all of the equipment works as it should turn off the MCCBs, fuse-switches, and
air circuit breakers (ACBs), take out the withdrawable units and look for any screws that are loose or parts that
are missing, make sure that the mechanisms work smoothly, and turn it back on and restore it.
This testing requires coordination with the power utility to turn off their supply at their transformer room to turn
off the main switchboard and check the ACBs at the main switchboard. The functional testing must cover all the
floor subboards.
Generator Testing and Lift Coordination
The manuscript delineates a particular scenario concerning emergency generator testing. To start the emergency
generator, you need to turn off the main power supply. The lift will stop when the main power is turned off.
This process makes sure that no one gets stuck in a lift when the main power goes out. The emergency generator
turns on by itself when the main power goes out. The generator runs for a long enough time (like 20 minutes) to
show that it works properly. The generator turns off by itself when the main power comes back on.
The 20-minute run time mentioned in the manuscript seems to be a requirement for that site. The EMSD (2025)
Wiring Code and relevant generator standards (like ISO 8528 (ISO, 2018)) set minimum run times for different
types of tests. Readers should check the requirements that apply to their own installations.
Temporary Lighting for WR2
The manuscript mentions a useful detail that is often missed. It needs to bring a portable diesel generator to give
temporary light because WR2 must do it at night and get the power back before morning.
WR2 testing (periodic inspection) usually happens at night or other times when people are not in the building to
avoid bothering them. But this means that the building will be without power for a few hours. For safety and to
let workers do the testing, there must be temporary lighting powered by a portable generator.
Post-Completion Activities
The manuscript outlines two final tasks after all testing has been finished and confirmed. Debris from installation,
like copper shavings, dust, and drilling swarf, can cause tracking, short circuits, and equipment to fail before its
time. Cleaning well is very important. A schematic diagram (also called a single-line diagram) must be shown
in the switch room so that operators and maintenance workers know how the system is set up.
Page 884
www.rsisinternational.org
INTERNATIONAL JOURNAL OF LATEST TECHNOLOGY IN ENGINEERING,
MANAGEMENT & APPLIED SCIENCE (IJLTEMAS)
ISSN 2278-2540 | DOI: 10.51583/IJLTEMAS | Volume XV, Issue IV, April 2026
Application to Data Centres
The manuscript states that the same basic T&C procedures apply to more complicated setups like data centers.
These are the basic electrical tests and T&C on the main switchboard, switches, UPS, changeover switches,
power panel units and other parts of the Data Centre. They also include simulating a fault to check the security
of the power supply.
In addition to other tests, data centers also test their uninterruptible power supplies (UPS), automatic transfer
switches (ATS), and standby generators by simulating fault conditions to make sure they work properly without
cutting off power to important loads.
WR2: Periodic Inspection and Testing
Definition and Regulatory Basis
WR2 stands for the regular checking, testing, and certification of low-voltage fixed electrical installations in
Hong Kong. The "R" stands for "regulation," and the "W" stands for "wiring." The Electricity Ordinance (Cap.
406) (Laws of Hong Kong, 2020) and the Electricity (Wiring) Regulations say that WR2 inspections must be
done.
How often WR2 inspections happen depends on the kind of building:
Every five years for hotels, hospitals, and public entertainment venues
Every five years for factories and industrial buildings
Buildings for business: every five years
For common areas in residential buildings, every ten years
If there are two transformers and one of them is more than 2500A, it must hire a REW(C0) to do WR2. REW B
can only work up to 2500A. There are different grades for Registered Electrical Workers (REWs). REW(B) can
work on installations with up to 2500A. REW(C0) is able to work on installations with more than 2500A, even
if they have two or more transformers
WR2 Procedure Based on the Author's Experience
The manuscript offers a firsthand narrative of WR2 procedures derived from the author's experiences at Lohas
Park and a supermarket in Tsuen Wan:
1. Working with the power company: The company turns off the power at their transformer room.
2. Night-time execution: WR2 must be done at night, and power must be restored before morning to cause
the least amount of disruption.
3. Temporary lighting: A portable diesel generator lights up the area while testing is going on.
4. Systematic testing: All relays are taken out and tested with secondary injection.
5. The order for switching: The power company should turn off their supply in the transformer room first
and then do WR2. After WR2 is done (the supposed incoming ACB and all downstream boards are off
power), the power company turns the power back on, then turns on the incoming ACB, and finally turns
on each downstream subboard.
Critical Safety Warning
The manuscript gives a strong warning about the risks of turning on. It is not dangerous to turn off the switch; it
is dangerous to turn it on. Before turning on the main switch, make sure that all of the downstream circuit
breakers are open. This warning is based on a basic rule of electrical safety: when you turn off a system, the load
is gradually disconnected, which means that the circuit breaker opens when the current is low or zero.
Page 885
www.rsisinternational.org
INTERNATIONAL JOURNAL OF LATEST TECHNOLOGY IN ENGINEERING,
MANAGEMENT & APPLIED SCIENCE (IJLTEMAS)
ISSN 2278-2540 | DOI: 10.51583/IJLTEMAS | Volume XV, Issue IV, April 2026
When you turn on the circuit breaker, it must close against the full inrush current of all the downstream loads,
such as transformers, motors, and capacitors. If there is a fault downstream, the circuit breaker will close on a
short circuit, which is dangerous because it can cause an arc flash.
Mandatory Testing Before Switching On
The manuscript states a crucial requirement prior to activation following maintenance or testing.
You need to check the megger test for all phases, from line to line, line to neutral and all insulated parts before
turning it on.
Before turning on any circuit that has been worked on, the insulation resistance must be checked. This proves
that no connections or damage were caused by accident while the work was being done.
Discrimination of Circuit Breakers
Definition and Importance
Discrimination, which is also known as selectivity or coordination, is the process of setting up overcurrent
protective devices (circuit breakers, fuses, relays) so that if there is a fault in the electrical system, the protective
device right before the fault clears it while all the other devices stay closed and power continues to flow to
healthy circuits.
It is very important when a fault happens, the far downstream breaker must trip before the nearer circuit breaker.
If the right discrimination is not used, a fault on a final circuit could trip the main incoming circuit breaker
instead of just the local sub-circuit breaker. This would cause the whole building to go dark and stop all
operations. This is especially important for places like data centers, hospitals, and air traffic control centers where
power must never go out.
Practical Experience: Discrimination Verification at CAD Headquarters
The manuscript talks about a project at CAD Headquarters, which is close to Hong Kong International Airport
and keeps an eye on air traffic. At CAD H/Q near the airport, I worked on a project with well-known contractor
RNB to make sure that all the main switchboards' relay settings were correct and that the right discrimination
was used when tripping.
As part of this project, we had to make sure that all the relay settings (current plug setting multiplier and time
multiplier) were working together correctly so that relays that are downstream trip faster than relays that are
upstream. The time-current characteristics of all devices in series do not overlap in a way that causes unwanted
upstream tripping.
Output of Discrimination Studies
It is necessary to make a report to CAD after checking. It means the discrimination verification was done.
A full report on discrimination research usually has:
A diagram of the electrical system on one line
Time-current characteristic curves for all safety devices
Tables of relay settings, such as plug setting, time multiplier, and instantaneous settings
Checking that the calculated fault current at each bus is less than the breaking capacity of all devices
A statement that the work follows the EMSD (2025) Wiring Code and other engineering standards such as
CIBSE (2004), IET (2018).
Page 886
www.rsisinternational.org
INTERNATIONAL JOURNAL OF LATEST TECHNOLOGY IN ENGINEERING,
MANAGEMENT & APPLIED SCIENCE (IJLTEMAS)
ISSN 2278-2540 | DOI: 10.51583/IJLTEMAS | Volume XV, Issue IV, April 2026
Methods for Achieving Discrimination
The manuscript talks about different kinds of starters that change starting currents and, as a result, discrimination.
DOL and assisted starters, like the star-delta starter, the auto transformer starter, the variable frequency (variable
speed starter), and the variable speed drive, are all soft starters that do not cause a sudden jump in starting current.
1. Direct-On-Line (DOL) starters send full voltage to the motor, which causes a high inrush current (usually
6–8 times full load current). This can make it hard to tell the difference because the high starting current
may be close to the setting of upstream protective devices.
2. Star-delta starters cut the starting current down to about 33% of the DOL starting current.
3. Auto-transformer starters let you choose the starting voltage (for example, 50%, 65%, or 80% of line
voltage) and lower the starting current at the same time.
4. Variable Frequency Drives (VFDs), also known as variable speed drives, frequency inverters, or soft
starters, slowly speed up the motor and only use a little more than full load current when starting.
VFDs and Energy Saving
The manuscript offers an intriguing operational perspective on variable frequency drives (VFDs) in heating,
ventilation, and air conditioning (HVAC) contexts. Instead of stopping the fan coil when the room temperature
is cool enough, let it run at a variable speed at a low speed. Proved saves more energy than frequently stopping
and starting the fan coil. This observation goes against the common belief that turning off a motor completely
saves the most energy. In fact, starting and stopping a lot:
1. Pulls a lot of current at the start each time
2. Puts thermal cycling stress on the motor windings
3. It might use more energy than running at a constant low speed.
VFDs let motors run at the lowest speed needed to keep setpoint conditions, which saves energy. VFD energy
savings can diminish due to installation errors and system overrides (Riskiawan et al., 2026). But the manuscript
does not give any numbers or references to back up the claimed energy savings, which is a problem.
Safety Precautions for Working on Live Electrical Installations
General Principles
The manuscript ends with important safety tips for working with electricity. The main idea is easy to understand,
but it must be followed strictly. Before you work on electrical installations, you need to turn off the power. But
there are times when you have to work on live parts, like when you need to test or measure something. In these
situations, extra care is needed.
Personal Protective Equipment (PPE)
The manuscript suggests:
1. Wearing insulated gloves—rated for the voltage in the area.
2. Do not wear metal glasses, wear plastic glasses instead. Metal frames can conduct electricity and cause
a shock or arc flash hazard.
3. Put an insulated mat on the floor while working on live parts, like the main switchboard, to make the
resistance to earth higher so that the current is lower if it flows on you.
The manuscript does not say what the voltage rating or testing frequency should be for insulated mats and gloves.
For more information, readers should look up the EMSD (2025) Wiring Code and the appropriate safety
standards, such as IEC 61111 for mats (IEC, 2009) and IEC 60903 for gloves (IEC, 2014).
Page 887
www.rsisinternational.org
INTERNATIONAL JOURNAL OF LATEST TECHNOLOGY IN ENGINEERING,
MANAGEMENT & APPLIED SCIENCE (IJLTEMAS)
ISSN 2278-2540 | DOI: 10.51583/IJLTEMAS | Volume XV, Issue IV, April 2026
Voltage Detection
The worker must make sure that the conductor is not live before touching it. Touch any parts that live with a pen
lamp, which will light up if the surface is live. This is a voltage pen or voltstick that lights up or beeps when it
gets close to a live conductor. The manuscript says that non-contact testers are good for initial checks, but a two-
pole voltage tester should be used to confirm before touching.
Lock-out/Tag-out (LOTO)
The manuscript stresses a key LOTO principle to put a hand lock on the switch so that no one can accidentally
turn it on while you have turned off the power.
The isolating switch should have a personal lock and tag on it, and the worker should keep the key. This stops
someone else from turning the circuit back on while work is going on. The manuscript also says that each worker
must put their own lock and tag on the isolating switch.
Permit-to-Work System
EMSD specifies the Permit to Work system in the EMSD Wiring Code when workers are working in an area
where there may be live electricity, such as inside a false ceiling.
A Permit-to-Work (PTW) is a written document that:
1. Tells you what work needs to be done
2. Tells where and how long it will be
3. Lists the safety measures and isolation points
4. Is signed by someone who has the right to do so, like a responsible engineer or supervisor
5. The worker knows about it
Before work starts, PTW makes sure that everyone knows about the risks and safety measures.
Limitations of the Study
Readers should be aware of the limitations of this paper, which is based on real-life experiences from
construction sites in Hong Kong.
(a) No photographic proof -- The original manuscript mentions several pictures (Photo 1, Photo 1b, Photo 1c,
Photo 3, and Photo 4) that are not included in the text that is available. These pictures would have been
helpful for showing how to build transformer rooms, plinths, ventilation systems, and control panels. These
pictures should be included in future revisions, or if they aren't available, they should be replaced with
schematic diagrams.
(b) No quantitative data -- The paper provides qualitative observations and procedural descriptions; however, it
lacks quantitative data, including measured insulation resistance values, earth fault loop impedance results,
ductor test readings, or comparative energy consumption figures for variable frequency drive (VFD) versus
stop-start operation. There are no measurements or references to back up the claim that "continuous low-
speed VFD operation proved save more energy than stop and start".
(c) Anecdotal case evidence -- The Kwun Tong case study demonstrating the repercussions of BEC non-
compliance is offered as a solitary anecdote, lacking supporting documentation such as correspondence,
regulatory notices, or financial records. The narrative is informative, but it fails to satisfy the evidentiary
criteria of formal case study research.
(d) References to rules that are not complete -- The paper talks about the EMSD Wiring Code, Cap. 610, the
Building Energy Code (BEC), and the BEC Technical Guide, but it doesn't say which edition, clause, or
Page 888
www.rsisinternational.org
INTERNATIONAL JOURNAL OF LATEST TECHNOLOGY IN ENGINEERING,
MANAGEMENT & APPLIED SCIENCE (IJLTEMAS)
ISSN 2278-2540 | DOI: 10.51583/IJLTEMAS | Volume XV, Issue IV, April 2026
publication date they are. Since these documents are updated from time to time, readers can't tell which
version of the requirements applies without checking on their own.
(e) Geographic scope -- The paper is only about Hong Kong's rules and building methods. The technical
principles (cable sizing, discrimination, testing procedures) are generally applicable; however, the specific
regulatory requirements (REA registration, WR2 frequencies, REW grading) are jurisdiction-specific and
should not be presumed to apply universally.
(f) No distinction between temporary and permanent -- The paper does not clearly separate the rules that apply
only to temporary transformer rooms on construction sites from those that apply to permanent installations.
For instance, are the WR2 inspection frequencies and REA requirements the same for both temporary and
permanent installations? This lack of clarity makes the paper less useful for people who only work with
temporary installations.
(g) No Discussion of transformer removal and decommissioning -- The paper talks about building, testing, and
using the temporary transformer room, but it doesn't say anything about how it will be taken down and
removed. This is a big problem because restoring the site and safely removing electrical infrastructure are
important steps in finishing the project.
CONCLUSION
This paper has attempted to connect the gap between theoretical electrical engineering concepts and the real-
world challenges of building temporary transformer rooms on large construction sites in Hong Kong. The authors
have used decades of combined field experience to write down the design features (weatherproofing, oil
containment, ventilation, security), technical procedures (cable sizing, T&C, WR2, discrimination), and
regulatory compliance requirements (Cap. 610, REA, BEC) that are necessary for a project to go smoothly.
The main point of this paper is that paying attention to details can save lives and money. Hiring qualified
professionals like REAs, REWs, and consulting engineers is very cheap compared to the money that could be
lost if a project takes too long to finish, if the property can't be rented out, if fines are imposed by the government,
or, worst of all, if someone dies and goes to jail and goes bankrupt. Also, the time spent on systematic testing
(insulation resistance, earth loop impedance, secondary injection, ductor testing) and formal verification
(discrimination studies, torque checks, polarity verification) stops failures from happening during operation,
which can have terrible effects.
There are still rules that apply to temporary electrical installations. The same safety rules, WR2 inspection
frequencies, and EMSD Wiring Code, Cap. 610 rules apply. The "temporary" label affects how the building is
built (making it weatherproof, easy to move, and easy to take down), but it doesn't change the rules or safety
standards.
The authors want people to think of this paper as a useful addition to the official codes and standards, not a
replacement for them. Every installation is different, and professional judgement based on the conditions at the
site must always come first. The principles documented here, from the 100 mm oil containment kerb to the pre-
energization insulation resistance test, are still the best practices that have been proven to work in the field over
many years.
As Hong Kong keeps building new areas, extending railways, and digging tunnels, the need for temporary high-
voltage electrical installations will only grow. The authors hope that this paper will help create a culture of safety,
compliance, and engineering excellence in the local construction industry. They also hope that future
professionals will build on and improve the practices described in this paper.
Recommendations for Future Work
Due to the limitations mentioned above, the following suggestions are made for future research and practice.
Page 889
www.rsisinternational.org
INTERNATIONAL JOURNAL OF LATEST TECHNOLOGY IN ENGINEERING,
MANAGEMENT & APPLIED SCIENCE (IJLTEMAS)
ISSN 2278-2540 | DOI: 10.51583/IJLTEMAS | Volume XV, Issue IV, April 2026
For Professionals
1. Get qualified professionals involved early. The costs of not following BEC rules or safety rules are much
higher than the costs of hiring experienced REA and consulting engineers. Getting involved early, before
site construction and during design, is very important.
2. Keep a record of all test results in an organised way. Keep logs of insulation resistance, earth loop impedance,
ductor tests, and relay injection results with the date on them. This paperwork shows that the rules were
followed and helps with finding faults.
3. Set up official LOTO and PTW processes. Even for short-term installations, strict lock-out/tag-out and permit-
to-work systems are necessary to keep workers safe. The EMSD Wiring Code sets the rules.
4. Check for discrimination by looking at the time-current curve. Do not think that overcurrent devices will work
together just because they have different ratings. Formal discrimination studies with plotted characteristic
curves are necessary.
5. Think about using VFDs for motor loads. In addition to the benefits of soft starting, VFDs save energy by
running continuously at low speeds in variable-torque applications like fans and pumps. However, it is
important to look at the costs of higher capital and the need to reduce harmonies.
For future studies
1. A study that compares numbers. A formal study that looks at insulation resistance values, earth fault loop
impedance, and ductor test results from several temporary transformer room installations would set empirical
benchmarks and find common ways that things go wrong.
2. A comparison of temporary and permanent requirements. A methodical comparison of regulatory requirements
(EMSD Wiring Code, Cap. 610, WR2) concerning temporary and permanent installations would elucidate
ambiguities within the existing framework.
3. How to measure how much energy VFDs save when they are only used for a short time. Field measures that
compare how much energy VFD-controlled fans and pumps use to DOL-controlled fans and pumps on
construction sites would back up the claimed savings.
4. Best practices for decommissioning and removing things. Research shows that documents safely to take down
temporary transformer rooms, such as draining oil, removing equipment, pulling cables, and restoring the site,
would fill a gap in the current literature.
5. Comparison across jurisdictions. A comparative analysis of temporary high-voltage electrical installation
regulations across various jurisdictions (Hong Kong, Singapore, UK, Australia) would elucidate best practices
and potential avenues for regulatory harmonisation.
ACKNOWLEDGEMENTS
The authors acknowledge the contributions of the many site engineers, electrical workers, and project managers
whose practical insights have informed this paper. Specific recognition is due to the project teams at Lohas Park,
the Tsuen Wan supermarket development, and the CAD Headquarters electrical protection discrimination
checking work with RNB near Hong Kong International Airport, where many of the procedures described were
developed and refined.
REFERENCES
1. CIBSE. (2004). CIBSE Guide K: Electricity in buildings. London: CIBSE.
2. CLP Power Hong Kong Limited. (2026). Supply Rules. Hong Kong: CLP Power Hong Kong Limited.
Page 890
www.rsisinternational.org
INTERNATIONAL JOURNAL OF LATEST TECHNOLOGY IN ENGINEERING,
MANAGEMENT & APPLIED SCIENCE (IJLTEMAS)
ISSN 2278-2540 | DOI: 10.51583/IJLTEMAS | Volume XV, Issue IV, April 2026
3. CLP Power Hong Kong Limited. (2025). Code of Practice 101 for Distribution Substation Design Version
16. Hong Kong: CLP Power Hong Kong Limited.
4. Development Bureau. (2024). Construction Site Safety Manual. Hong Kong: Government Printer.
5. Electrical and Mechanical Services Department (EMSD). (2025). Code of Practice for the Electricity
(Wiring) Regulations. Hong Kong: Government Printer.
6. Electrical and Mechanical Services Department. (2024). Code of Practice for Energy Efficiency of
Building Services Installation. Hong Kong: Government Printer.
7. Electrical and Mechanical Services Department. (2024a). Code of Practice for Building Energy Audit.
Hong Kong: Government Printer.
8. Hora, A. (2024). Test polarity: detecting positive and negative tests. In Companion Proceedings of the
32nd ACM International Conference on the Foundations of Software Engineering (pp. 537-541).
9. Juris, J. S., Durán-Tovar, I. С., Tello-Maita, J., & Marulanda-Guerra, A. (2024). Insulation system
diagnosis in power transformers using DGA analysis and Megger DC tests. Ingeniería e
Investigación, 44(1), e103210.
10. Laws of Hong Kong. (2020). Cap. 406 Electricity Ordinance. Available at
https://www.elegislation.gov.hk/hk/cap406.
11. Laws of Hong Kong. (2013). Cap. 610 Building Energy Efficiency Regulation. Available at
https://www.elegislation.gov.hk/hk/cap610.
12. International Electrotechnical Commission (IEC). (2025). IEC 60364 Electrical Installations for
Buildings. Geneva: IEC.
13. International Electrotechnical Commission (IEC). (2014). IEC 60903 Live Working - Electrical
Insulating Gloves. Geneva: IEC.
14. International Electrotechnical Commission (IEC). (2009). IEC 61111 Live Working - Electrical
Insulating Mats. Geneva: IEC.
15. Institution of Engineering and Technology. (2018). BS 7671 - 18th Edition The IET Wiring Regulations.
London: Institution of Engineering and Technology.
16. International Organization for Standardization (ISO). (2018). ISO 8528 Reciprocating Internal
Combustion Engine Driven Alternating Current Generating Sets. Geneva: ISO.
17. Neamt, L., Neamt, A., & Chiver, O. (2021). Improved Procedure for Earth Fault Loop Impedance
Measurement in TN Low-Voltage Network. Energies, 14(1), 205.
18. Riskiawan, H. Y., Anwar, S., Setyohadi, D. P. S., Arifin, S., Widiawan, B., Jannah, A. N. H., & Setiawan,
A. B. (2026). Field Evaluation of an IoT-VFD Smart Ventilation System for Energy-Efficient Rice Seed
Storage. Sinkron: jurnal dan penelitian teknik informatika, 10(2), 1025-1037.