Temporary Transformer Room Installations for Construction Sites: Cable Sizing, Testing, WR2, and Circuit Breaker Discrimination
Authors
Ir. Dr. Samuel Kwok Piu LIP
Founder and Managing Director of Lordray Engineering Company Limited (MY)
Dr. Wing Cheung TANG
Adjunct Professor of Spectrum International University College, Malaysia (MY)
Ir. Jonathan WONG
General Manager of Paul Y. (E&M) Contractors Ltd (MY)
Article Information
DOI: 10.51583/IJLTEMAS.2026.150400079
Subject Category: Engineering
Volume/Issue: 15/4 | Page No: 874-890
Publication Timeline
Submitted: 2026-05-12
Published: 2026-05-12
Abstract
Large-scale construction sites frequently require electrical power exceeding the capacity of a single 400A three-phase feeder. In such contexts, power utilities typically supply a small-capacity 11kV transformer (e.g., 200–300 kVA) housed within a purpose-built temporary transformer room. This paper examines the practical engineering considerations surrounding the construction of such temporary transformer rooms, with particular attention to design specifications for weatherproofing, oil containment, ventilation, and security. Beyond physical infrastructure, the paper addresses essential technical procedures including cable sizing in accordance with the EMSD Wiring Code, the role of the Registered Energy Assessor (REA) under Cap. 610, testing and commissioning (T&C) protocols, periodic inspection and testing (WR2), and the critical engineering task of circuit breaker discrimination. Drawing on authentic field experience from Hong Kong construction sites, this paper aims to share practical knowledge with industry peers, highlighting both technical requirements and common pitfalls that may lead to financial losses, regulatory non-compliance, or safety hazards. The paper concludes that early engagement of qualified professionals, rigorous adherence to testing protocols, and systematic verification of protective device coordination are essential to successful temporary electrical installations.
Keywords
building energy code, cable sizing, circuit breaker discrimination, temporary transformer room, testing and commissioning, WR2
Downloads
References
1. CIBSE. (2004). CIBSE Guide K: Electricity in buildings. London: CIBSE. [Google Scholar] [Crossref]
2. CLP Power Hong Kong Limited. (2026). Supply Rules. Hong Kong: CLP Power Hong Kong Limited. [Google Scholar] [Crossref]
3. CLP Power Hong Kong Limited. (2025). Code of Practice 101 for Distribution Substation Design Version 16. Hong Kong: CLP Power Hong Kong Limited. [Google Scholar] [Crossref]
4. Development Bureau. (2024). Construction Site Safety Manual. Hong Kong: Government Printer. [Google Scholar] [Crossref]
5. Electrical and Mechanical Services Department (EMSD). (2025). Code of Practice for the Electricity (Wiring) Regulations. Hong Kong: Government Printer. [Google Scholar] [Crossref]
6. Electrical and Mechanical Services Department. (2024). Code of Practice for Energy Efficiency of Building Services Installation. Hong Kong: Government Printer. [Google Scholar] [Crossref]
7. Electrical and Mechanical Services Department. (2024a). Code of Practice for Building Energy Audit. Hong Kong: Government Printer. [Google Scholar] [Crossref]
8. Hora, A. (2024). Test polarity: detecting positive and negative tests. In Companion Proceedings of the 32nd ACM International Conference on the Foundations of Software Engineering (pp. 537-541). [Google Scholar] [Crossref]
9. Juris, J. S., Durán-Tovar, I. С., Tello-Maita, J., & Marulanda-Guerra, A. (2024). Insulation system diagnosis in power transformers using DGA analysis and Megger DC tests. Ingeniería e Investigación, 44(1), e103210. [Google Scholar] [Crossref]
10. Laws of Hong Kong. (2020). Cap. 406 Electricity Ordinance. Available at https://www.elegislation.gov.hk/hk/cap406. [Google Scholar] [Crossref]
11. Laws of Hong Kong. (2013). Cap. 610 Building Energy Efficiency Regulation. Available at https://www.elegislation.gov.hk/hk/cap610. [Google Scholar] [Crossref]
12. International Electrotechnical Commission (IEC). (2025). IEC 60364 Electrical Installations for Buildings. Geneva: IEC. [Google Scholar] [Crossref]
13. International Electrotechnical Commission (IEC). (2014). IEC 60903 Live Working - Electrical Insulating Gloves. Geneva: IEC. [Google Scholar] [Crossref]
14. International Electrotechnical Commission (IEC). (2009). IEC 61111 Live Working - Electrical Insulating Mats. Geneva: IEC. [Google Scholar] [Crossref]
15. Institution of Engineering and Technology. (2018). BS 7671 - 18th Edition The IET Wiring Regulations. London: Institution of Engineering and Technology. [Google Scholar] [Crossref]
16. International Organization for Standardization (ISO). (2018). ISO 8528 Reciprocating Internal Combustion Engine Driven Alternating Current Generating Sets. Geneva: ISO. [Google Scholar] [Crossref]
17. Neamt, L., Neamt, A., & Chiver, O. (2021). Improved Procedure for Earth Fault Loop Impedance Measurement in TN Low-Voltage Network. Energies, 14(1), 205. [Google Scholar] [Crossref]
18. Riskiawan, H. Y., Anwar, S., Setyohadi, D. P. S., Arifin, S., Widiawan, B., Jannah, A. N. H., & Setiawan, A. B. (2026). Field Evaluation of an IoT-VFD Smart Ventilation System for Energy-Efficient Rice Seed Storage. Sinkron: jurnal dan penelitian teknik informatika, 10(2), 1025-1037. [Google Scholar] [Crossref]
Metrics
Views & Downloads
Similar Articles
- Performance Analysis of Silicon PV Array Using Infrared Thermography and Detecting Temperature Non-Uniformities
- Dynamic Capabilities and Digital Transformation Performance: The Role of Organizational Agility in the Public Sector
- Comparative Effectiveness of Neural Mobilization Versus Positional Release Technique in Cervical Radiculopathy – An Experimental Study
- Soil Moisture Mapping of Solano Nueva Vizcaya: A Comparison and Review
- Silent Assistance for Emergencies (SAFE): A Mobile-Based Emergency Reporting Application for the Deaf and Mute Community